R-2A Activity · President's Budget PB2027

SSDS MK2 Product Development/Combat Systems Integration

Activity a0·Project 2178 — QRCC·PE 0604755N·U.S. Navy
FY2027 Request
$114.8M
▼ 8.9% vs FY2026
HitchAI read

This activity requests $114.8M in FY2027, 79% of project 2178, down 8.9% on FY2026. The R-2A exhibit describes it across FY2026–FY2027, including what the FY2027 money is planned to buy.

FY2027 Request
$114.8M
▼ 8.9% vs FY2026
FY2026 Enacted
$126.1M
▲ 17% vs FY2025
FY2025 Actual
$107.7M
Prior year
Planned work

What the FY2027 request buys

Verbatim from the R-2A exhibit for project 2178 of PE 0604755N. This is the budget justification's own description of work that has not happened yet — the one thing no other level of the budget carries.

FY2027 planned work

For Build 12+ - Continue efforts for systems engineering, design, and qualification of common computing infrastructure components/designs supporting SSDS platforms. - Continue efforts for systems engineering capability insertions, to include requirements development/updates, use cases, trade studies and conduct Systems Engineering Technical Review (SETR) events as required: - Continue Integration of applicable common software including Battle Decision Aids - Adaptable Deck Launch (ESSM Block 2 Phase 2 (Optimized)) - Continue AN/SLQ-32(V)7 (Electronic Warfare Improvement) - Continue CEC Increment 2 (CG4/5) - Continue integration/lifecycle engineering efforts for Combat System Build 12 I in support of the following capability insertions: - AN/SPY-6(V) integration - AN/SLQ-32(V)6 (Electronic Warfare Improvement) - GPNTS/GEDMS - SSDS virtualization (previously containerization) - CEC Increment 2 (CG2/3) - Complete CAC2S Afloat mission capability design, development, test, and certification of the Coalition/NATO Link 22 interface, the TTNT interface, the UxV interfaces to process both Full Motion Video (FMV) and Still Imagery Products (SIP), and the web-based CEC product for non-CEC ship classes to provide real-time netted-sensor tracks/targets. - Continue efforts on Software Support Activities (SSA) to include cybersecurity updates, CANES certifications, and support for four (4) software update builds released per year. - Initiate SPY-6 EPIC 3 Improved Air Surveillance Tracking and Electronic Protection [EASR Epic 3] Optimized air warfare performance for improved self-defense, Advanced Electronic Protection

FY2026 to FY2027 change

The FY 2026 to FY2027 adjustments include an increase to support integration of SPY-6 EPIC 3 in SSDS but is offset by reductions resulting in a net decrease of $11.287. This decrease impacts CAC2S Afloat by $3.2M resulting in a delay in delivery of the Distributed Common Ground System - Navy (DCGS-N) interface, Coalition/NATO Link 22 interface, and the Tactical Targeting Network Technology (TTNT) implementation. We are extending the development timeline for these interfaces to multi-year efforts to fit within the existing budget. The remaining $7.787M reduction freezes SSDS cyber capability development except for testing and minimum limited high priority software corrections.

Before the request year

FY2026: the year under way

Prior-year accomplishments and current-year plans from the same exhibit. Context for the FY2027 plan, not a series — an activity partitions its project exactly in the request year, but can under-cover it in earlier years.

FY2026 plans — current year

For Build 12+ - Continue efforts for systems engineering, design, and qualification of common computing infrastructure components/designs supporting SSDS platforms. - Continue efforts for systems engineering capability insertions, to include requirements development/updates, use cases, trade studies and conduct Systems Engineering Technical Review (SETR) events as required: - Integration of applicable common software including Battle Decision Aids - Adaptable Deck Launch (ESSM Block 2 Phase 2 (Optimized)) - Initiate AN/SLQ-32(V)7 (Electronic Warfare Improvement) - Initiate CEC Increment 2 (CG4/5) - Continue integration/lifecycle engineering efforts for Combat System Build 12 I in support of the following capability insertions: - AN/SPY-6(V) integration - AN/SLQ-32(V)6 (Electronic Warfare Improvement) - GPNTS/GEDMS - SSDS virtualization (previously containerization) - CEC Increment 2 (CG2/3) - Complete the CAC2S Afloat development, integration, test, and certification efforts for the Shipboard ISR-T interfaces to include Minotaur/MTC-A and DCGS-N which will be released to the Fleet. - Initiate the new mission capability design, development, test, and certification of the Coalition/NATO Link 22 interface, the TTNT interface, the UxV interfaces to process both Full Motion Video (FMV) and Still Imagery Products (SIP), and the web-based CEC product for non-CEC ship classes to provide real-time netted-sensor tracks/targets. - Continue efforts on Software Support Activities (SSA) to include cybersecurity updates, consolidated Afloat Network Enterprise Services (CANES) certifications, and support for four (4) software update builds released per year.

Money

Three years, and no five-year plan

An R-2A activity publishes the prior year, the current year and the budget year. The FYDP outyears exist at project and program-element level and are deliberately absent here rather than inferred. Estimate types are colored and never summed into one figure.

2550751001250107.7FY25ACTUAL126.1FY26ENACTED114.8FY27REQUEST
Actual Enacted Request
Fiscal YearEstimate TypeAmount ($M)
FY2025Actual107.7
FY2026Enacted126.1
FY2027Request114.8

This activity is 79% of project 2178's FY2027 request and 74% of PE 0604755N's. In the request year the activities under a project sum to it exactly; in the current year they under-cover it in about 9% of cases, so an activity's delta can legitimately exceed its parent's and the two must not be compared row to row.

Where this sits

2 activities in project 2178

Every R-2A line of this project, largest FY2027 request first. Linked where the activity has enough of its own narrative to carry a page; the rest are shown in full on the project page.

SSDS MK2 Product Development/Combat Systems Integration — this activity$114.8M ▼ 9%
SSDS MK2 Development Test & Evaluation$30.0M ▲ 10%
Source
FY2027 Department of the Navy RDT&E Budget Justification · Exhibit R-2A · PE 0604755N, project 2178 (President's Budget PB2027). Congressional marks are recorded on the program element, never on an activity.