RDT&E Project · President's Budget PB2027

Afloat C-UAS

FY2027 Request
$228.4M
▲ 480% vs FY2026
HitchAI read

Project 2077 — Afloat C-UAS requests $228.4M in FY2027, 77% of the $296.3M requested for program element 0604756N, up 480% on FY2026. 1 R-2A activity decomposes the request. Program Office is the largest named R-3 performer at $3.4M, 1.5% of the project's FY2027 R-3 total.

MarketCounter-UAS

Matched on this project's title. A title match, not a curated taxonomy — narrative-only matches are not shown at all rather than shown with a caveat nobody reads. No market size is quoted here: a market spans appropriations far beyond this program element.

FY2027 Request
$228.4M
▲ 480% vs FY2026
FY2026 Enacted
$39.4M
No FY2025 funding
FY2025 Actual
$0.0M
Prior year
Project detail

What project 2077 buys

Afloat Counter Unmanned Aerial Systems (C-UAS) was established to meet an urgent operational need and funds the acquisition, testing, integration, and fielding of prototype C-UAS's to provide a lower cost defense in-depth solution to negate the UAS threats. The FY 2026 budget for Afloat C-UAS (2077) included $39.407 million of discretionary and $200.000 million of mandatory funding for a total of $239.407 million. The $200.000 million mandatory funds enabled the acquisition of the prototype systems identified through the testing that occurred in FY 2024 and FY 2025. In FY 2026, the program continued developing and testing C-UAS systems to pace the evolving threat. Further information for this reconciliation request is provided in Section 20010 (Readiness) of the Reconciliation Exhibit. The FY 2027 request for C-UAS will fund fielding the systems acquired in FY 2026 and acquire systems to support two carrier strike groups consisting of four to five deploying ships and one expeditionary strike group consisting of three deploying ships in for fielding in FY 2027 and FY 2028.

R-3 lines of work
  • Product Development
  • Support
  • Management Services
Funding trajectory

Project 2077 funding, FY2025–FY2031

Prior years are actuals, the budget year is the request, and the outyears are the FYDP plan. Estimate types are colored and never summed into one figure. Projects carry the full five-year plan; the activities inside them stop at the budget year.

5010015020000.0FY25ACTUAL39.4FY26ENACTED228.4FY27REQUEST225.6FY28225.5FY29234.5FY30239.0FY31
Actual Enacted Request Outyear (FYDP)
Fiscal YearEstimate TypeAmount ($M)
FY2025Actual0.0
FY2026Enacted39.4
FY2027Request228.4
FY2028Outyear225.6
FY2029Outyear225.5
FY2030Outyear234.5
FY2031Outyear239.0
Inside the project

1 accomplishment / planned program

The R-2A exhibit — the only level of the budget that describes work that has not happened yet. Activities carry the prior, current and budget year only, no five-year plan. Each describes FY2027 work in enough detail to have its own page; the rest are shown here in full. Coverage is partial across the corpus, so count activities, never total them.

FY2025 actual$0.0M
FY2026 enacted$39.4M
FY2027 request$228.4M

Acquire C-UAS systems to support fielding on two carrier strike groups consisting of four to five deploying ships each and one expeditionary strike group consisting of three deploying ships for fielding in FY 2027 and 2028. Fielding the C-UAS prototype systems that were acquired in FY 2026. C-UAS engineering support, development and…

Read the FY2027 plan →
Who's building it

Named performers on project 2077

Performers named in the R-3 exhibit under this project. Share is of the project's whole FY2027 R-3 total — the same denominator the program-element split uses, so the two read on one scale and will not sum to 100% when unnamed or government work is in the mix. Budget-justification contract funding, not obligations.

Program Office
$3.4M · 1.5%