U.S. Navy requests $3.4M in FY2027, sustained across the five-year plan. In the FY2027 defense authorization, the House funded it in full; the Senate funded it in full; House appropriators funded it in full. NAWCAD leads the industry work.

FY2027 Request
$3.4M
▼ 9.0% vs FY2026
FY2026 Enacted
$3.7M
▼ 91% vs FY2025
FY2025 Actual
$42.9M
Prior year

Roll-up of 3 projects. Projects are the summable leaves — the PE total is their sum, never added to it.

For fiscal year 2027, the U.S. Navy is requesting $3.4M for Navigation/Id System under RDT&E program element 0604777N, down 9.0% from FY2026.

Funding trajectory

Funding profile, FY2025–FY2031

Prior years are actuals, the budget year is the request, and the outyears are the FYDP plan. Estimate types are colored and never summed into one figure.

25042.9FY25ACTUAL3.7FY26ENACTED3.4FY27REQUEST4.4FY284.3FY294.2FY304.3FY31
Actual Enacted Request Outyear (FYDP)
Fiscal YearEstimate TypeAmount ($M)
FY2025Actual42.9
FY2026Enacted3.7
FY2027Request3.4
FY2028Outyear4.4
FY2029Outyear4.3
FY2030Outyear4.2
FY2031Outyear4.3
Where it sits

Acquisition lifecycle

This program is funded in RDT&E Budget Activity 5 — System Development & Demonstration.

Complete
Research
BA 1–2
Complete
Advanced Technology
BA 3
Complete
Prototyping
BA 4
Current
Development & Fielding
BA 5–7
Inside the program element

3 projects roll up into PE 0604777N

Projects are the summable leaves — the PE total is their sum, never added to it. Program elements and projects carry the full five-year plan; activities stop at the budget year. This PE moves -9% overall, which can hide much larger swings below.

The whole program

SUPT is funded on 13 lines across 4 appropriations

This program element requests nothing for SUPT in FY2027. The program is still funded — $646.2M of it — but on other lines, which usually means the work is transferring.

Also funded hereTypeComponentFY2027 $M
Sub Periscope, Imaging and Supt Equip ProgProcurementNavy344.9
Exp Indirect Fire Gen Supt Wpn SysRDT&ENavy115.2
RDT&E Acft SuptRDT&ENavy51.6
Nav & Electro-Optical SuptRDT&ENavy39.4
Comm & Elec Infrastructure SuptProcurementNavy37.6
Submarine Supt Equip ProgRDT&ENavy33.2
Naval Tact Cmd Supt Sys (NTCSS)ProcurementNavy10.1
Naval War Col Strategic Studies SuptRDT&ENavy9.6
SUPT totalNavy646.2

Lines whose title names the program. 5 further lines only mention SUPT in their justification text — those fund something else and are deliberately excluded from the total.

Congressional action

Congressional marks

Committee marks on the FY2027 request. Adds and cuts are reconciled in conference before they become law.

RequestPresident's Budget
$3.4M
House NDAA (HASC)HASC
$3.4M full · +$0
Senate NDAA (SASC)SASC
$3.4M full · +$0
House Approps (HAC-D)HAC_D
$3.4M full · +$0
unresolved as of 2026-07-27. These are FY2027 authorization marks (NDAA); appropriations and the conference agreement may differ.
Who's building it

Where the FY2027 request goes

Performers named in the R-3 exhibit, resolved into industry, government-lab, and unspecified shares. Budget-justification contract funding, not obligations.

NAWCAD
$3.4M · 99%
Primary Hardware Development
Where FY2027 funding flowsShare$M
Industry primes99%3.4
Other / unspecified1.0%0.0
FY2027 request100%3.4
See NAWCAD's full federal contract ledger members
Program detail

Mission & acquisition strategy

AN/BVY-1 Integrated Submarine Imaging System (ISIS) adds new capabilities via the Technical Insertion (TI)/Advanced Processing Build (APB) process, while working with partner Submarine Warfare Federated Tactical System (SWFTS) programs to realign software development according to Development Security Operations (DevSecOps) software processes. The Navy is pursuing a cloud-enabled containerization architecture transformation across SWFTS (PE 0604503N Project 0219, Project 0236, Project 0253, and Project 0775) to increase operational agility and resiliency at the speed of relevance.

The Single Acquisition Management Plan (SAMP) for the ISIS Program TI-20/22/24 with Mast is approved 07 Jul 2017. The Program Streamlined Acquisition Plan with Services (PSTRAP-M) for ISIS TI-26/28/30 is approved 08 Mar 2024. The Acquisition Program Baseline Agreement (APBA) for ISIS Program TI-26 Increment with APB-25 & APB-27 is approved 01 May 2024. The ISIS will provide mission critical, all weather, visual, and electronic search, digital image management, indication, warning, and platform architecture interface capabilities for SSN 688, SSN 21, SSN 774, SSN 826 and SSGN class submarines.

Project 1253, 0676, 0253 — Combat Ident System
  • Product Development
  • Support
  • Test and Evaluation
  • Management Services
Ask Hitch

Ask this program element

Answers are generated from the figures on this page — the FY2027 justification exhibits and the marks tracked above — and nothing else is consulted. Confirm any figure against the cited exhibit before you use it externally.

H
Questions this page can answer
How does the FY2027 request compare with FY2026, and what does the five-year plan show?What did the FY2027 NDAA committees do to this request?Which project inside PE 0604777N is growing fastest, and which is shrinking?How is the FY2027 request split between industry and government performers?

This page carries the budget justification and the NDAA marks — nothing else. For what NAWCAD has actually been obligated, the ledger is at hitchintel.com/vendors; for live solicitations, hitchintel.com/opportunities. Both are member surfaces.

Provenance

Cite this page

Sources
FY2027 Department of the Navy RDT&E Budget Justification · Exhibits R-2 / R-3 · PE 0604777N (President's Budget PB2027) — and FY2027 NDAA committee marks, as tracked 2026-07-27.
Suggested citation
HitchAI, "Navigation/Id System (PE 0604777N)," federal budget intelligence, PB2027 vintage. hitchintel.com/programs/0604777N
Machine access
Markdown twin /programs/0604777N.md · MCP mcp.hitchintel.combudget_get_program_element, budget_get_cong_marks
FY2027 Request
$1.9M
▲ 5.6% vs FY2026
FY2026 Enacted
$1.8M
▼ 15% vs FY2025
FY2025 Actual
$2.1M
Prior year

Combat Ident System — one RDT&E project inside PE 0604777N. Congressional marks are recorded on the program element, not on a project.

Project 1253 — Combat Ident System — requests $1.9M in FY2027, 55% of the $3.4M requested for program element 0604777N. Year over year it grows 5.6% against FY2026.

Funding trajectory

Project 1253 funding, FY2025–FY2031

Prior years are actuals, the budget year is the request, and the outyears are the FYDP plan. Estimate types are colored and never summed into one figure. Projects carry the full five-year plan; the activities inside them stop at the budget year.

02.1FY25ACTUAL1.8FY26ENACTED1.9FY27REQUEST1.9FY282.0FY292.0FY302.0FY31
Actual Enacted Request Outyear (FYDP)
Fiscal YearEstimate TypeAmount ($M)
FY2025Actual2.1
FY2026Enacted1.8
FY2027Request1.9
FY2028Outyear1.9
FY2029Outyear2.0
FY2030Outyear2.0
FY2031Outyear2.0
Inside the project

2 accomplishments / planned programs

The R-2A exhibit. Activities carry the prior, current and budget year only — no five-year plan — and they are descriptive: coverage is partial and they do not always add back to the project, so count them, never total them.

Mode 5 Systems Engineering and Integrated Logistics Support (ILS)▲ 10%
FY2025 actual$0.8M
FY2026 enacted$0.8M
FY2027 request$0.9M

FY2027 planned work Continue development, testing, certification, and integration of the APX-123A tech refresh, RT-2087/ZPX (Micro IFF), and KIV-79. Continue research into deployment of enhanced non-cooperative CID capabilities. Research into Crypto Modernization 2 (CM2) compliance for all equipment.

FY2026 to FY2027 change FY 2027 increase in funds due to APX-123 Tech Refresh logistics documentation requirements.

FY2026 plans — current year Continue development, testing, certification, and integration of the APX-123A tech refresh, RT-2087/ZPX (Micro IFF), and KIV-79. Continue research into deployment of enhanced non-cooperative CID capabilities. Research into Crypto Modernization 2 (CM2) compliance for all equipment.

Mark XIIA Upgrade Developmental Test & Operational Test▲ 2%
FY2025 actual$1.3M
FY2026 enacted$0.9M
FY2027 request$1.0M

FY2027 planned work Continue RT-2087/ZPX and KIV-79 testing, integration, and certifications. Continue research into deployment of micro interrogator/reverse Mode 5 capability. Continue Mode 5 integration and testing on platforms.

FY2026 to FY2027 change No significant changes.

FY2026 plans — current year Continue RT-2087/ZPX and KIV-79 testing, integration, and certifications. Continue research into deployment of micro interrogator/reverse Mode 5 capability. Continue Mode 5 integration and testing on platforms.

Who's building it

Named performers on project 1253

Performers named in the R-3 exhibit under this project. Share is of the project's whole FY2027 R-3 total — the same denominator the program-element split uses, so the two read on one scale and will not sum to 100% when unnamed or government work is in the mix. Budget-justification contract funding, not obligations.

NAWCAD
$1.9M · 100%
Project detail

What project 1253 buys

MARK (MK) XIIA Mode 5 provides secure cooperative combat identification via Identification Friend or Foe (IFF). Mode 5 was developed in cooperation with North Atlantic Treaty Organization, with the DoW implementation governed by AIMS 03-1000A, AIMS 03-1000B and USN requirements defined in ORD # 577-06-01. IFF product improvements are designed to be installed through obsolescence mitigations, upgrades, technical refreshes, and deficiency correction studies, which in turn become engineering changes to IFF interrogators and transponders and their associated cryptographic material. Standards governed by AIMS 17-1000 and Crypto Modernization (CM) are required to be incorporated in future engineering changes. The Navy MK XIIA Mode 5 program was approved for entry in Systems Development and Demonstration phase in August 2003 and into the Production and Deployment Phase and Low Rate Initial Production in July 2006, and Full Rate Production July 2012. The Navy Mode 5 program achieved Initial Operational Capability (IOC) in 2012 in accordance with the ORD. Mode 5 capable equipment was fielded in USN/USMC platforms in accordance with Joint Requirements Oversight Council Memorandums (047-07, 122-08 and 108-13) in support of Joint Mode 5 IOC in 2014 and Joint Full Operational Capability in FY 2020. In order to maintain cooperative encrypted Combat Identification (CID) capabilities across the fleet, sustainment and new development efforts must continue into the foreseeable future. Studies for future leading-edge non-cooperative CID technologies are being investigated. RDTE articles include Mode 5 cryptographic modules and associated hardware and software changes for IFF interrogators and transponders, including, but not limited to: AN/APX-118/123, AN/APX-119, AN/APX-111, RT-2087/ZPX, and all associated test and support equipment. RDTE units are required for government and contractor labs to support aircraft and ship integrations, test sites, test aircraft, and unmanned aircraft systems.

R-3 lines of work
  • Product Development
  • Support
  • Test and Evaluation
  • Management Services
FY2027 Request
$1.5M
▼ 22% vs FY2026
FY2026 Enacted
$2.0M
▼ 38% vs FY2025
FY2025 Actual
$3.2M
Prior year

Improve ID Development — one RDT&E project inside PE 0604777N. Congressional marks are recorded on the program element, not on a project.

Project 0676 — Improve ID Development — requests $1.5M in FY2027, 45% of the $3.4M requested for program element 0604777N. Year over year it falls 22% against FY2026.

Funding trajectory

Project 0676 funding, FY2025–FY2031

Prior years are actuals, the budget year is the request, and the outyears are the FYDP plan. Estimate types are colored and never summed into one figure. Projects carry the full five-year plan; the activities inside them stop at the budget year.

03.2FY25ACTUAL2.0FY26ENACTED1.5FY27REQUEST2.5FY282.4FY292.2FY302.2FY31
Actual Enacted Request Outyear (FYDP)
Fiscal YearEstimate TypeAmount ($M)
FY2025Actual3.2
FY2026Enacted2.0
FY2027Request1.5
FY2028Outyear2.5
FY2029Outyear2.4
FY2030Outyear2.2
FY2031Outyear2.2
Inside the project

4 accomplishments / planned programs

The R-2A exhibit. Activities carry the prior, current and budget year only — no five-year plan — and they are descriptive: coverage is partial and they do not always add back to the project, so count them, never total them.

Mark XIIA Mode 5 and Mode S Improvement for AN/UPX-29(V)▲ 2%
FY2025 actual$0.6M
FY2026 enacted$0.6M
FY2027 request$0.6M

FY2027 planned work Continue AN/UPX-29(V) Interrogator System integration testing with Mode 5/Mode S Capable AN/UPX-50 Digital Interrogator obsolescence upgrades in preparation for deployment to Aegis and Ship Self Defense System (SSDS) Platforms on LPD, LHA and CVN Class ships. Continue AN/UPX-46(V) Interrogator System integration testing with Mode 5/Mode S Capable AN/UPX-45 Digital Interrogator obsolescence upgrades for deployment to COMBATTS-21 Platforms. Continue to evaluate inter-operability test data to validate planned combat systems design changes and capability updates.

FY2026 to FY2027 change No significant changes.

FY2026 plans — current year Commence AN/UPX-29(V) Interrogator System integration testing with Mode 5/Mode S Capable AN/UPX-50 Digital Interrogator obsolescence upgrades in preparation for deployment to Aegis and Ship Self Defense System (SSDS) Platforms on LPD, LHA and CVN Class ships. Continue AN/UPX-46(V) Interrogator System integration testing with Mode 5/Mode S Capable AN/UPX-45 Digital Interrogator obsolescence upgrades for deployment to COMBATTS-21 Platforms. Continue to evaluate inter-operability test data to validate planned combat systems design changes and capability updates.

AN/UPX-29(V) Management Support▼ 49%
FY2025 actual$0.7M
FY2026 enacted$0.8M
FY2027 request$0.4M

FY2027 planned work Continue logistics and technical data management for the AN/UPX-29(V) Mode 5/Mode S integration. Continue integration testing of Safety related Software update on AEGIS and Ships Self Defense System (SSDS) baselines. Develop improved cyber designs and cyber security controls for implementation in future software releases. Assess cyber software assurance tools for applicability to IFF products.

FY2026 to FY2027 change FY 2027 funding decrease to support higher Navy priorities.

FY2026 plans — current year Continue logistics and technical data management for the AN/UPX-29(V) Mode 5/Mode S integration. Develop improved cyber designs and cyber security controls for implementation in future software releases. Assess cyber software assurance tools for applicability to IFF products.

UPX-36 Engineering Change Proposal - Mode 5 Capable▼ 12%
FY2025 actual$1.2M
FY2026 enacted$0.6M
FY2027 request$0.5M

FY2027 planned work Conduct Integration and certification tests at Land Based Test Sites

FY2026 to FY2027 change FY 2027 funding decrease to support higher Navy priorities.

FY2026 plans — current year Finalize system retrofit plans and certifications.

Radar Track Discriminator System (RTDS) UPX-34A ECP Part I
FY2025 actual$0.6M
FY2026 enacted$0.0M
FY2027 request$0.0M
Who's building it

Named performers on project 0676

Performers named in the R-3 exhibit under this project. Share is of the project's whole FY2027 R-3 total — the same denominator the program-element split uses, so the two read on one scale and will not sum to 100% when unnamed or government work is in the mix. Budget-justification contract funding, not obligations.

NAWCAD
$1.5M · 98%
Project detail

What project 0676 buys

Reliable and secure navigation and positive identification (ID) systems are essential elements of battle management in the naval environment. In addition to providing platform identification for weapons employment, the Navy requires secure, jam resistant Identification Friend or Foe (IFF) systems for battle group air defense management and Air Traffic Control. The Improved ID Development project addresses the Mark XIIA Mode 5 and Mode Select (S) upgrades to the existing AN/UPX-29(V) Mark XII family of systems that is Joint and North Atlantic Treaty Organization interoperable, as well as modernization of the DDG 1000 Zumwalt Class IFF Sensor Suite. The AN/UPX-29(V) Interrogator System is comprised of the Interrogator Set AN/UPX-24(V), OE-120()/UPX Antenna Group, and Mark XII or Mark XIIA equipment including but not limited to AN/UPX-41(C), AN/UPX-45(C), or AN/UPX-50(C) Digital Interrogators (DI) and associated equipment. The DDG 1000 IFF Sensor Suite is comprised of three electronically scanned array (ESA) antennas, one UPX-42(C) Interrogator, and three RT-1912(C)/APX Transponders. Additionally, the Improved ID Development project may include product improvements designed to be installed through upgrade and deficiency correction studies, which in turn become engineering changes to other IFF solutions.

R-3 lines of work
  • Product Development
  • Support
  • Test and Evaluation
  • Management Services
FY2027 Request
$0.0M
No FY2026 funding
FY2026 Enacted
$0.0M
▼ 100% vs FY2025
FY2025 Actual
$37.7M
Prior year

Nav & Electro-Optical Supt — one RDT&E project inside PE 0604777N. Congressional marks are recorded on the program element, not on a project.

Project 0253 — Nav & Electro-Optical Supt — requests $0.0M in FY2027, 0.0% of the $3.4M requested for program element 0604777N.

Funding trajectory

Project 0253 funding, FY2025–FY2031

Prior years are actuals, the budget year is the request, and the outyears are the FYDP plan. Estimate types are colored and never summed into one figure. Projects carry the full five-year plan; the activities inside them stop at the budget year.

25037.7FY25ACTUAL0.0FY26ENACTED0.0FY27REQUEST0.0FY280.0FY290.0FY300.0FY31
Actual Enacted Request Outyear (FYDP)
Fiscal YearEstimate TypeAmount ($M)
FY2025Actual37.7
FY2026Enacted0.0
FY2027Request0.0
FY2028Outyear0.0
FY2029Outyear0.0
FY2030Outyear0.0
FY2031Outyear0.0
Inside the project

3 accomplishments / planned programs

The R-2A exhibit. Activities carry the prior, current and budget year only — no five-year plan — and they are descriptive: coverage is partial and they do not always add back to the project, so count them, never total them.

ISIS and Photonics common software and hardware capabilities development and obsolescence
FY2025 actual$27.9M
FY2026 enacted$0.0M
FY2027 request$0.0M
Type 24 Mast
FY2025 actual$9.0M
FY2026 enacted$0.0M
FY2027 request$0.0M
Imaging Systems Test Efforts
FY2025 actual$0.8M
FY2026 enacted$0.0M
FY2027 request$0.0M
Project detail

What project 0253 buys

AN/BVY-1 Integrated Submarine Imaging System (ISIS) adds new capabilities via the Technical Insertion (TI)/Advanced Processing Build (APB) process, while working with partner Submarine Warfare Federated Tactical System (SWFTS) programs to realign software development according to Development Security Operations (DevSecOps) software processes. The Navy is pursuing a cloud-enabled containerization architecture transformation across SWFTS (PE 0604503N Project 0219, Project 0236, Project 0253, and Project 0775) to increase operational agility and resiliency at the speed of relevance. The Legacy Mast Improvements Program specifically focuses on incorporating mature technologies and design improvements into legacy masts; this effort provides substantial improvements to the large inventory of photonics and imaging masts. Both programs ensure that submarines can conduct operations in high intensity littoral environments, intelligence gathering, real time imagery, and support the safe and effective employment of surveillance and weapons systems. The Navigation and Electro-Optical (E-O) program enables littoral operations by procuring ISIS, the production of low-profile photonics masts (Low Profile Photonics Mast (LPPM), Type 20, and Type 24), the maintenance and sustainment of periscope and legacy photonic masts, the production and sustainment of Universal Modular Mast Systems and Dip Loops, and the development of the ISIS inboard processing components of the Submarine Warfare Federated Tactical System (SWFTS). The Department of the Navy established the ISIS to rapidly field the Type 18 periscope, RADAR rangefinder, Type 8 Mod 4 Infrared (IR) periscope system, and integrate existing periscope imagery systems into a single imaging system for installation on board SSN 688 class and SEA WOLF class submarines. The ISIS baseline also includes the Imaging System with the Photonics mast (PM) and all configurations of low-profile photonics masts onboard VIRGINIA and Photonics Mast Variant (PMV) onboard SSGN class submarines and ISIS on SSBN class submarines. The PM, LPPM, and PMV design exploit a wide portion of the electro-magnetic spectrum through advanced E-O and thermal imaging and Electronic Warfare Support (ES)/communications intercept.

R-3 lines of work
  • Product Development
  • Test and Evaluation
  • Management Services