RDT&E Project · President's Budget PB2027

Air Vehicle Block 4 Planning & Sys Eng

Project 2568·PE 0604840M — F-35B C2D2·U.S. Navy·BA7
FY2027 Request
$162.8M
▲ 93% vs FY2026
HitchAI read

Project 2568 — Air Vehicle Block 4 Planning & Sys Eng requests $162.8M in FY2027, 35% of the $469.8M requested for program element 0604840M, up 93% on FY2026. 1 R-2A activity decomposes the request. Lockheed Martin is the largest named R-3 performer at $118.8M, 73% of the project's FY2027 R-3 total.

MarketAircraft & Aero Components (mfg)

Matched on this project's title. A title match, not a curated taxonomy — narrative-only matches are not shown at all rather than shown with a caveat nobody reads. No market size is quoted here: a market spans appropriations far beyond this program element.

FY2027 Request
$162.8M
▲ 93% vs FY2026
FY2026 Enacted
$84.2M
▼ 38% vs FY2025
FY2025 Actual
$135.0M
Prior year
Project detail

What project 2568 buys

The F-35 Air Vehicle Program Management Office (AV PMO) development portfolio includes efforts to improve the F-35 air vehicle lethality, survivability, and interoperability in response to emerging threats outlined in the National Security Strategy and Operational Plans. F-35 Block 4 Modernization is designed to counter the full spectrum of evolving near-peer enemy threats to ensure US and Allied forces have freedom of operation even in the face of advanced adversary Anti-Access/Area Denial (A2/AD) capabilities. As designed, Block 4 consists of three principal lines of effort: development of software-based capabilities, development and integration of new and modernized aircraft hardware that enable the development of new capabilities, and new weapons integration. Efforts under the Air Vehicle / Block 4 Planning and Systems Engineering project range from requirements decomposition and preliminary design of capabilities through completion of Developmental Flight Test. These activities are a continuation of the previous Block 4 developmental contracts, and include activities required to enable the successful completion of Flight Test, to include select facility upgrades required for research, development, test and evaluation. Block 4 upgraded capabilities and continuous improvements will maintain Air System viability against the evolving threats indicated in the Electronic Warfare Initial Capabilities Document (ICD), the Fifth Generation Fighter Modernization ICD, and the Block 4 Capability Development Document (CDD). Additionally, the Block 4 capabilities will reduce life cycle cost, improve Air System Integration, and improve operational suitability. Weapons integration efforts under this project deliver increased lethality, effectiveness, situational awareness and operational flexibility, and include M-code GPS compatibility, Advanced Integrated Fire Control implementation, network enabled weapons, increased Air-to-Air missile carriage, and employment envelope expansion. Beyond Line of Sight (BLOS) efforts under this project will deliver increased range and effectiveness of the F-35, by providing improved interoperability across joint platforms within a highly contested environment.

R-3 lines of work
  • Product Development
  • Support
Funding trajectory

Project 2568 funding, FY2025–FY2031

Prior years are actuals, the budget year is the request, and the outyears are the FYDP plan. Estimate types are colored and never summed into one figure. Projects carry the full five-year plan; the activities inside them stop at the budget year.

1002003004000135.0FY25ACTUAL84.2FY26ENACTED162.8FY27REQUEST406.6FY28366.3FY29310.6FY30238.1FY31
Actual Enacted Request Outyear (FYDP)
Fiscal YearEstimate TypeAmount ($M)
FY2025Actual135.0
FY2026Enacted84.2
FY2027Request162.8
FY2028Outyear406.6
FY2029Outyear366.3
FY2030Outyear310.6
FY2031Outyear238.1
Inside the project

1 accomplishment / planned program

The R-2A exhibit — the only level of the budget that describes work that has not happened yet. Activities carry the prior, current and budget year only, no five-year plan. Each describes FY2027 work in enough detail to have its own page; the rest are shown here in full. Coverage is partial across the corpus, so count activities, never total them.

FY2025 actual$135.0M
FY2026 enacted$84.2M
FY2027 request$162.8M

Continue and expand Agile development of capabilities through Developmental and Operational Flight Test. Continue requirements decomposition, preliminary design, and engineering and manufacturing development activities for advanced Block 4 capability improvements to Radar, Electronic Warfare, Electro-Optical/Infrared (EO/IR), and…

Read the FY2027 plan →
Who's building it

Named performers on project 2568

Performers named in the R-3 exhibit under this project. Share is of the project's whole FY2027 R-3 total — the same denominator the program-element split uses, so the two read on one scale and will not sum to 100% when unnamed or government work is in the mix. Budget-justification contract funding, not obligations.

Lockheed Martin
$118.8M · 73%