R-2A Activity · President's Budget PB2027

C2 Data Layer Program Management

Activity a2·Project C2E — C2 DATA·PE 0605332A·U.S. Army
FY2027 Request
$19.1M
◆ New start in FY2027
HitchAI read

This activity requests $19.1M in FY2027, 7.7% of project C2E — a new start with no prior-year and no current-year money. The R-2A exhibit describes it across FY2027, including what the FY2027 money is planned to buy.

New start

This activity requests $19.1M in FY2027 with no prior-year and no current-year funding. There is no incumbent line to compare it with — it did not exist before this President's Budget.

FY2027 Request
$19.1M
President's Budget
Planned work

What the FY2027 request buys

Verbatim from the R-2A exhibit for project C2E of PE 0605332A. This is the budget justification's own description of work that has not happened yet — the one thing no other level of the budget carries.

FY2027 planned work

Funds labor to support facilitation of continuous competition, cybersecurity compliance assessments, software materiel release and associated updates, logistics support, program oversight and risk management.

FY2026 to FY2027 change

FY 2027 increase due to project established under a new funding structure to support NGC2 Data Layer efforts. Increase from prior funded year due to increased staffing requirements to support emerging needs associated with integrating the full stack NGC2 capability and accelerating the deployment timeline.

Money

Three years, and no five-year plan

An R-2A activity publishes the prior year, the current year and the budget year. The FYDP outyears exist at project and program-element level and are deliberately absent here rather than inferred. Estimate types are colored and never summed into one figure.

019.1FY27REQUEST
Request
Fiscal YearEstimate TypeAmount ($M)
FY2027Request19.1

This activity is 7.7% of project C2E's FY2027 request and 6.2% of PE 0605332A's. In the request year the activities under a project sum to it exactly; in the current year they under-cover it in about 9% of cases, so an activity's delta can legitimately exceed its parent's and the two must not be compared row to row.

Where this sits

3 activities in project C2E

Every R-2A line of this project, largest FY2027 request first. Linked where the activity has enough of its own narrative to carry a page; the rest are shown in full on the project page.

C2 Data Layer Continuous Integration and Continuous Deployment (CI/CD)$220.3M NEW
C2 Data Layer Program Management — this activity$19.1M NEW
C2 Data Layer Test/Evaluation/Validation/Verification (TEVV)$8.2M NEW
Source
FY2027 Department of the Army RDT&E Budget Justification · Exhibit R-2A · PE 0605332A, project C2E (President's Budget PB2027). Congressional marks are recorded on the program element, never on an activity.
Machine access
Markdown twin /programs/0605332A/C2E/a2.md · MCP mcp.hitchintel.combudget_get_activity