R-2A Activity · President's Budget PB2027

Ground Systems

FY2027 Request
$25.8M
▲ 47% vs FY2026
HitchAI read

This activity requests $25.8M in FY2027, 38% of project E25, up 47% on FY2026. The R-2A exhibit describes it across FY2025–FY2027, including what the FY2027 money is planned to buy.

FY2027 Request
$25.8M
▲ 47% vs FY2026
FY2026 Enacted
$17.6M
▲ 16% vs FY2025
FY2025 Actual
$15.1M
Prior year
Planned work

What the FY2027 request buys

Verbatim from the R-2A exhibit for project E25 of PE 0708045A. This is the budget justification's own description of work that has not happened yet — the one thing no other level of the budget carries.

FY2027 planned work

Continue addressing advanced manufacturing processes for high-performance / lower-weight armor materials for Army platforms and ramp up efforts focused on manufacturing advanced systems for ground platforms. Continue effort to reduce RDX production requirements for the MICLIC to improve manufacturability and effectiveness while reducing cost. Initiate efforts to reduce manufacturing costs and lead times for electronic components for ground platforms.

FY2026 to FY2027 change

The increase in funding reflects ongoing efforts to reduce RDX production requirements for the MICLIC to improve manufacturability and effectiveness while reducing cost, reduce manufacturing costs and lead times for electronic components for ground platforms, and address advanced manufacturing processes for high-performance / lower-weight armor materials for ground platforms.

Before the request year

FY2025–FY2026: what came before

Prior-year accomplishments and current-year plans from the same exhibit. Context for the FY2027 plan, not a series — an activity partitions its project exactly in the request year, but can under-cover it in earlier years.

FY2026 plans — current year

Continue addressing advanced manufacturing processes for high-performance / lower-weight armor materials for Army platforms and ramp up efforts focused on manufacturing advanced systems for ground platforms. Continue effort to reduce RDX production requirements for the Mine-Clearing Line Charge (MICLIC) to improve manufacturability and effectiveness while reducing cost.

FY2025 accomplishments

Program plans will continue efforts advancing digital thread capabilities and addressing advanced manufacturing processes for high performance / lower weight armor materials. Ramp up the development of manufacturing processes for advanced systems for ground platforms.

Money

Three years, and no five-year plan

An R-2A activity publishes the prior year, the current year and the budget year. The FYDP outyears exist at project and program-element level and are deliberately absent here rather than inferred. Estimate types are colored and never summed into one figure.

25015.1FY25ACTUAL17.6FY26ENACTED25.8FY27REQUEST
Actual Enacted Request
Fiscal YearEstimate TypeAmount ($M)
FY2025Actual15.1
FY2026Enacted17.6
FY2027Request25.8

This activity is 38% of project E25's FY2027 request and 38% of PE 0708045A's. In the request year the activities under a project sum to it exactly; in the current year they under-cover it in about 9% of cases, so an activity's delta can legitimately exceed its parent's and the two must not be compared row to row.

Where this sits

5 activities in project E25

Every R-2A line of this project, largest FY2027 request first. Linked where the activity has enough of its own narrative to carry a page; the rest are shown in full on the project page.

Ground Systems — this activity$25.8M ▲ 47%
Weapon Systems$23.5M ▲ 46%
Networks and Command, Control, Communications and Intelligence$8.3M ▼ 45%
Aviation Systems$5.3M ▼ 5%
Soldier Systems$5.2M ▼ 54%
Source
FY2027 Department of the Army RDT&E Budget Justification · Exhibit R-2A · PE 0708045A, project E25 (President's Budget PB2027). Congressional marks are recorded on the program element, never on an activity.