Roll-up of 2 projects. Projects are the summable leaves — the PE total is their sum, never added to it.
For fiscal year 2027, the U.S. Army is requesting $68.1M for End Item Industrial Preparedness Activities under RDT&E program element 0708045A, down 25% from FY2026. In the FY2027 defense authorization, House moved to raise it to $85.1M.
Funding profile, FY2025–FY2031
Prior years are actuals, the budget year is the request, and the outyears are the FYDP plan. Estimate types are colored and never summed into one figure.
| Fiscal Year | Estimate Type | Amount ($M) |
|---|---|---|
| FY2025 | Actual | 84.8 |
| FY2026 | Enacted | 90.8 |
| FY2027 | Request | 68.1 |
| FY2028 | Outyear | 68.8 |
| FY2029 | Outyear | 69.3 |
| FY2030 | Outyear | 70.0 |
| FY2031 | Outyear | 70.7 |
Acquisition lifecycle
This program is funded in RDT&E Budget Activity 7 — Operational System Development.
2 projects roll up into PE 0708045A
Projects are the summable leaves — the PE total is their sum, never added to it. Program elements and projects carry the full five-year plan; activities stop at the budget year. This PE moves -25% overall, which can hide much larger swings below.
MANTECH INITIATIVES (CA)
The request is contested
Committee marks on the FY2027 request. Adds and cuts are reconciled in conference before they become law.
Where the FY2027 request goes
Performers named in the R-3 exhibit, resolved into industry, government-lab, and unspecified shares. Budget-justification contract funding, not obligations.
| Where FY2027 funding flows | Share | $M |
|---|---|---|
| Other / unspecified | 100% | 68.1 |
| FY2027 request | 100% | 68.1 |
Mission & acquisition strategy
This Program Element (PE) funds the Army Manufacturing Technology (ManTech) program, which develops, demonstrates, and transitions manufacturing technologies and processes that enable improvements in producibility and affordability of components and subsystems of Army weapon platforms and systems. Army ManTech matures technologies from Manufacturing Readiness Level (MRL) 4, which is the capability of producing the technology in a laboratory environment, up to MRL 7, which is the capability of producing systems, subsystems, or components in a production-relevant environment.
Not applicable for this item.
- Product Development
Ask this program element
Answers are generated from the figures on this page — the FY2027 justification exhibits and the marks tracked above — and nothing else is consulted. Confirm any figure against the cited exhibit before you use it externally.
This page carries the budget justification and the NDAA marks — nothing else. For what a contractor has actually been obligated, the ledger is at hitchintel.com/vendors; for live solicitations, hitchintel.com/opportunities. Both are member surfaces.
Cite this page
/programs/0708045A.md · MCP mcp.hitchintel.com → budget_get_program_element, budget_get_cong_marksMfg Science & Tech — one RDT&E project inside PE 0708045A. Congressional marks are recorded on the program element, not on a project.
Project E25 — Mfg Science & Tech — requests $68.1M in FY2027, 100% of the $68.1M requested for program element 0708045A. Year over year it grows 3.4% against FY2026.
Project E25 funding, FY2025–FY2031
Prior years are actuals, the budget year is the request, and the outyears are the FYDP plan. Estimate types are colored and never summed into one figure. Projects carry the full five-year plan; the activities inside them stop at the budget year.
| Fiscal Year | Estimate Type | Amount ($M) |
|---|---|---|
| FY2025 | Actual | 64.9 |
| FY2026 | Enacted | 65.8 |
| FY2027 | Request | 68.1 |
| FY2028 | Outyear | 68.8 |
| FY2029 | Outyear | 69.3 |
| FY2030 | Outyear | 70.0 |
| FY2031 | Outyear | 70.7 |
5 accomplishments / planned programs
The R-2A exhibit. Activities carry the prior, current and budget year only — no five-year plan — and they are descriptive: coverage is partial and they do not always add back to the project, so count them, never total them. Opening lines only here — the full year-by-year narrative is on the project page.
Continue cost reduction of anti-jammer antennas, eliminating the interlayer epoxy in the manufacture of compound semiconductors to dramatically improve transmission and simplify the FPA fabrication process, and simplifying the manufacturing process and improving yield, cost, and performance of IR sensor layers utilizing direct bond…
Continue supporting AMD capabilities focused on the affordability and producibility of DE systems, cannon tube production optimization, improving cold-plate brazing for high-power radar systems, and additive manufacturing processes for high-power radar systems, munitions, and scramjet components. Initiate efforts to reduce cost and…
Read the FY2027 plan →Continue addressing advanced manufacturing processes for high-performance / lower-weight armor materials for Army platforms and ramp up efforts focused on manufacturing advanced systems for ground platforms. Continue effort to reduce RDX production requirements for the MICLIC to improve manufacturability and effectiveness while reducing…
Read the FY2027 plan →Program plans will continue to mature manufacturing processes and capabilities supporting rotary aircraft components and UAS, leveraging advanced manufacturing techniques (e.g., additive manufacturing, cold spray).
Continue production process improvements for next-generation 6.8mm ammunition and production process improvements for the manufacturing of low-cost flame-resistant textiles.
What project E25 buys
This Project develops and demonstrates manufacturing technologies and processes that enable improvements in producibility and affordability of emerging and enabling components and subsystems of Army ground and air platforms, Soldier systems, weapons systems, air and missile defense systems, and sensors and electronics. Work is performed to advance the state-of-the-art, leveraging automation in manufacturing processing and fabrication techniques for coatings, multifunctional materials, and structural elements for Army-specific applications.
- Product Development
MANTECH INITIATIVES (CA) — one RDT&E project inside PE 0708045A. Congressional marks are recorded on the program element, not on a project.
Project EA2 — MANTECH INITIATIVES (CA) — requests — in FY2027, 0.0% of the $68.1M requested for program element 0708045A. Year over year it falls 100% against FY2026.
Project EA2 funding, FY2025–FY2026
Prior years are actuals, the budget year is the request, and the outyears are the FYDP plan. Estimate types are colored and never summed into one figure. Projects carry the full five-year plan; the activities inside them stop at the budget year.
| Fiscal Year | Estimate Type | Amount ($M) |
|---|---|---|
| FY2025 | Actual | 19.8 |
| FY2026 | Enacted | 25.0 |
What project EA2 buys
Congressional Interest Item funding provided for ManTech Initiatives. These efforts will test and evaluate transparent armor laminated material processing methodologies and develop manufacturing methodologies for laminated transparent armor material, and establish material/process qualification plans for advanced manufacturing of traditionally large, difficult-to-additively manufacture forged components for CH-47, UH-60, and AH-64.
- Product Development