R-2A Activity · President's Budget PB2027

Space Force TENCAP

FY2027 Request
$10.6M
◆ New start in FY2027
HitchAI read

This activity requests $10.6M in FY2027, 23% of project 642611 — a new start with no prior-year and no current-year money. The R-2A exhibit describes it across FY2027, including what the FY2027 money is planned to buy.

New start

This activity requests $10.6M in FY2027 with no prior-year and no current-year funding. There is no incumbent line to compare it with — it did not exist before this President's Budget.

FY2027 Request
$10.6M
No FY2026 funding
FY2026 Enacted
$0.0M
In law
Planned work

What the FY2027 request buys

Verbatim from the R-2A exhibit for project 642611 of PE 1206438SF. This is the budget justification's own description of work that has not happened yet — the one thing no other level of the budget carries.

FY2027 planned work

-Exploit existing and future National, global, and Non-Traditional systems in air, space and cyber domains for operational and tactical applications by rapidly prototyping and providing capability demonstrations. The program consists of multiple small projects supporting the Space Force warfighter. Projects are designed to transition to warfighters or national intelligence agencies for operational use and to appropriate acquisition Programs of Record for sustainment and further development. SF TENCAP projects influence the design and operation of current and future National, global, and Non-Traditional systems in air, space, and cyber while providing Space Domain Awareness and Offensive and Defensive Space Control capabilities to warfighters and intelligence organizations. -SF TENCAP requirements and existing resources may be rapidly re-prioritized in response to emerging warfighter needs.

FY2026 to FY2027 change

FY 2027 funding increased due to addition of Space Force TENCAP in this Program Element. Efforts were previously funded in Research, Development, Test and Evaluation, Air Force Program Element 0207247F (AF TENCAP).

Money

Three years, and no five-year plan

An R-2A activity publishes the prior year, the current year and the budget year. The FYDP outyears exist at project and program-element level and are deliberately absent here rather than inferred. Estimate types are colored and never summed into one figure.

00.0FY26ENACTED10.6FY27REQUEST
Enacted Request
Fiscal YearEstimate TypeAmount ($M)
FY2026Enacted0.0
FY2027Request10.6

This activity is 23% of project 642611's FY2027 request and 17% of PE 1206438SF's. In the request year the activities under a project sum to it exactly; in the current year they under-cover it in about 9% of cases, so an activity's delta can legitimately exceed its parent's and the two must not be compared row to row.

Where this sits

3 activities in project 642611

Every R-2A line of this project, largest FY2027 request first. Linked where the activity has enough of its own narrative to carry a page; the rest are shown in full on the project page.

Source
FY2027 Department of the Air Force RDT&E Budget Justification · Exhibit R-2A · PE 1206438SF, project 642611 (President's Budget PB2027). Congressional marks are recorded on the program element, never on an activity.
Machine access
Markdown twin /programs/1206438SF/642611/a2.md · MCP mcp.hitchintel.combudget_get_activity