$50.9M
◆ Development crest → decline
HitchAI read

U.S. Air Force requests $50.9M in FY2027 (down from a FY2026 peak), before stepping down 94% across the five-year plan. In the FY2027 defense authorization, the House funded it in full; the Senate funded it in full; House appropriators added 22% (to $62.0M). L3Harris leads the industry work.

FY2027 Request
$50.9M
▼ 7.7% vs FY2026
FY2026 Enacted
$55.1M
▲ 5.2% vs FY2025
FY2025 Actual
$52.4M
Prior year

For fiscal year 2027, the U.S. Air Force is requesting $50.9M for E-4B Aircraft Modernization under RDT&E program element 0302015F, down 7.7% from FY2026.

Funding trajectory

Funding profile, FY2025–FY2031

Prior years are actuals, the budget year is the request, and the outyears are the FYDP plan. Estimate types are colored and never summed into one figure.

2550052.4FY25ACTUAL55.1FY26ENACTED50.9FY27REQUEST21.8FY282.7FY292.7FY302.8FY31
Actual Enacted Request Outyear (FYDP)
Fiscal YearEstimate TypeAmount ($M)
FY2025Actual52.4
FY2026Enacted55.1
FY2027Request50.9
FY2028Outyear21.8
FY2029Outyear2.7
FY2030Outyear2.7
FY2031Outyear2.8
Where it sits

Acquisition lifecycle

This program is funded in RDT&E Budget Activity 7 — Operational System Development.

Complete
Research
BA 1–2
Complete
Advanced Technology
BA 3
Complete
Prototyping
BA 4
Current
Development & Fielding
BA 5–7
Inside the program element

1 project rolls up into PE 0302015F

Projects are the summable leaves — the PE total is their sum, never added to it. Program elements and projects carry the full five-year plan; activities stop at the budget year. This PE moves -8% overall, which can hide much larger swings below.

Project 674777

E-4B Aircraft Modernization

$50.9MFY2027 request ▼ 8%
FY2025 actual$52.4M
FY2026 enacted$55.1M
FY2027 request$50.9M
Product Development

The four (4) aircraft E-4B National Airborne Operations Center (NAOC) fleet satisfies the military need for an airborne operations center with communications capabilities permitting military and civilian leadership to monitor and control military and civil national assets during all phases of conflict (nuclear and non-nuclear) or natural disaster. The E-4B NAOC fleet also satisfies the military requirement to provide a highly survivable node of the National Military Command System (NMCS). This program's developmental efforts include, but are not limited to, upgrades and enhancements to aircraft structures, propulsion system, fuel system, environmental control system, electrical generation and distribution systems, flight safety and navigation systems (with their associated communications equipment), and the Systems Integration Lab. Modifications may enhance the aircraft's mission capabilities necessary for the E-4B fleet to execute its mission, to include but not limited to those necessary for the Senior Leadership Command, Control and Communications System (SLC3S), National Leadership Command Capability (NLCC), and Nuclear Command, Control, and Communications (NC3). Funds may also be used to explore and develop modifications, upgrades, and future systems required to meet evolving mission requirements. This budget supports the following developmental modifications and studies/projects currently underway or planned for accomplishment: - Survivable Super High Frequency (SSHF) will upgrade and replace portions of the E-4B's Jam-Resistant Secure Communications (JRSC) system to meet existing Presidential Policy Directive (PPD)-35 and National Security Presidential Directive (NSPD)-51/Homeland Security Presidential Directive (HSPD)-20 requirements and to ensure continued connectivity and interoperability as satellite and communications infrastructure evolves. Expected modifications include, but are not limited to, component and sub-system upgrades and replaces portions of the current Super High Frequency (SHF) system that are obsolete or near end of service life. A replacement to the SHF system is required as secure, survivable communications capability transitions from the Defense Satellite Communications System (DSCS). A risk-reduction study was completed in FY 2019 to further define the acquisition strategy of the SSHF program.

Accomplishments / planned programs (R-2A) — prior, current and budget year only
Survivable SHF▼ 44%
FY2025 actual$43.3M
FY2026 enacted$41.0M
FY2027 request$23.0M

FY2027 planned work -Complete Ku development activities -Begin Ku integration, testing and installation activities

FY2026 to FY2027 change Funding decrease due to completion of SPECTRE 2A prototype installation, leaving only Ku Band effort requiring funding.

FY2026 plans — current year - Continue design/begin prototype of Ku-band system - Installation of 2A prototype

E-4B Systems Integration Laboratory (SIL)▲ 71%
FY2025 actual$9.0M
FY2026 enacted$8.0M
FY2027 request$13.7M

FY2027 planned work -Completion of APIP backbone certification -Continuation of Mission Equipment Section systems development and integration -Begin legacy network and communication integration

FY2026 to FY2027 change Funding increased is due to ramp up of the legacy network and communication integration.

FY2026 plans — current year - Continue APIP backbone integration into SIL - Begin Block 1 incorporate/develop the Mission Equipment Section systems

Touchscreen Executive Phone-Airborne (TXP-A)▲ 133%
FY2025 actual$0.0M
FY2026 enacted$6.1M
FY2027 request$14.2M

FY2027 planned work -Continue TXP-A development effort -Begin TXP-A integration and testing

FY2026 to FY2027 change Funding increased due to the ramp-up of integration activities and development.

FY2026 plans — current year -Begin development of the TXP-A solution

Congressional action

Congressional marks

Committee marks on the FY2027 request. Adds and cuts are reconciled in conference before they become law.

RequestPresident's Budget
$50.9M
House NDAA (HASC)HASC
$50.9M full · +$0
Senate NDAA (SASC)SASC
$50.9M full · +$0
House Approps (HAC-D)HAC_D
$62.0M +$11.1M · +22%
▲ $11.1M chamber gap — unresolved as of 2026-07-27. These are FY2027 authorization marks (NDAA); appropriations and the conference agreement may differ.
Who's building it

Where the FY2027 request goes

Performers named in the R-3 exhibit, resolved into industry, government-lab, and unspecified shares. Budget-justification contract funding, not obligations.

L3Harris
$23.0M · 45%
Survivable SHF · CPFF
SMS
$13.7M · 27%
E-4B SIL · CPFF
Where FY2027 funding flowsShare$M
Industry primes72%36.6
Other / unspecified28%14.2
FY2027 request100%50.9
See L3Harris's full federal contract ledger members
Program detail

Mission & acquisition strategy

The four (4) aircraft E-4B National Airborne Operations Center (NAOC) fleet satisfies the military need for an airborne operations center with communications capabilities permitting military and civilian leadership to monitor and control military and civil national assets during all phases of conflict (nuclear and non-nuclear) or natural disaster. The E-4B NAOC fleet also satisfies the military requirement to provide a highly survivable node of the National Military Command System (NMCS).

Acquisition Strategy: The acquisition strategy for each specific modification differs based on the urgency of the requirement, definition of the capability, and technology readiness level of the components. The Acquisition Strategy for Survivable SHF Inc 1A and 1B is Section 804 Middle Tier Acquisition (MTA). Increment 1 Rapid Prototype MTA was approved in April 2019 and is in the procurement phase. Increment 2 Rapid Prototype MTA was approved in December 2021, but was split into two increments and ultimately transitioned into two ACAT III acquisition programs, 2B (Ku-band/X-band) in 1st quarter FY 2025 and 2A (Spectre) in 3rd quarter FY 2025.

Project 674777 — E-4B Aircraft Modernization
  • Product Development
Ask Hitch

Ask this program element

Answers are generated from the figures on this page — the FY2027 justification exhibits and the marks tracked above — and nothing else is consulted. Confirm any figure against the cited exhibit before you use it externally.

H
Questions this page can answer
How does the FY2027 request compare with FY2026, and what does the five-year plan show?What did the FY2027 NDAA committees do to this request?How is the FY2027 request split between industry and government performers?In plain terms, what is this program element for and how is it being acquired?

This page carries the budget justification and the NDAA marks — nothing else. For what L3Harris has actually been obligated, the ledger is at hitchintel.com/vendors; for live solicitations, hitchintel.com/opportunities. Both are member surfaces.

Provenance

Cite this page

Sources
FY2027 Department of the Air Force RDT&E Budget Justification · Exhibits R-2 / R-3 · PE 0302015F (President's Budget PB2027) — and FY2027 NDAA committee marks, as tracked 2026-07-27.
Suggested citation
HitchAI, "E-4B Aircraft Modernization (PE 0302015F)," federal budget intelligence, PB2027 vintage. hitchintel.com/programs/0302015F
Machine access
Markdown twin /programs/0302015F.md · MCP mcp.hitchintel.combudget_get_program_element, budget_get_cong_marks