HitchAI read

U.S. Army funding falls 91% to a $5.5M request in FY2027 (down from a FY2026 peak), sustained across the five-year plan. In the FY2027 defense authorization, the House funded it in full; the Senate funded it in full; House appropriators added 271% (to $20.5M).

FY2027 Request
$5.5M
▼ 91% vs FY2026
FY2026 Enacted
$63.7M
▲ 12% vs FY2025
FY2025 Actual
$57.0M
Prior year

Roll-up of 3 projects. Projects are the summable leaves — the PE total is their sum, never added to it.

For fiscal year 2027, the U.S. Army is requesting $5.5M for Command, Control, Communications Systems - Eng Dev under RDT&E program element 0604805A, down 91% from FY2026.

Funding trajectory

Funding profile, FY2025–FY2031

Prior years are actuals, the budget year is the request, and the outyears are the FYDP plan. Estimate types are colored and never summed into one figure.

2550057.0FY25ACTUAL63.7FY26ENACTED5.5FY27REQUEST6.0FY285.2FY295.2FY305.2FY31
Actual Enacted Request Outyear (FYDP)
Fiscal YearEstimate TypeAmount ($M)
FY2025Actual57.0
FY2026Enacted63.7
FY2027Request5.5
FY2028Outyear6.0
FY2029Outyear5.2
FY2030Outyear5.2
FY2031Outyear5.2
Where it sits

Acquisition lifecycle

This program is funded in RDT&E Budget Activity 5 — System Development & Demonstration.

Complete
Research
BA 1–2
Complete
Advanced Technology
BA 3
Complete
Prototyping
BA 4
Current
Development & Fielding
BA 5–7
Inside the program element

3 projects roll up into PE 0604805A

Projects are the summable leaves — the PE total is their sum, never added to it. Program elements and projects carry the full five-year plan; activities stop at the budget year. This PE moves -91% overall, which can hide much larger swings below.

Congressional action

Congressional marks

Committee marks on the FY2027 request. Adds and cuts are reconciled in conference before they become law.

RequestPresident's Budget
$5.5M
House NDAA (HASC)HASC
$5.5M full · +$0
Senate NDAA (SASC)SASC
$5.5M full · +$0
House Approps (HAC-D)HAC_D
$20.5M +$15.0M · +271%
▲ $15.0M chamber gap — unresolved as of 2026-07-27. These are FY2027 authorization marks (NDAA); appropriations and the conference agreement may differ.
Who's building it

Where the FY2027 request goes

Performers named in the R-3 exhibit, resolved into industry, government-lab, and unspecified shares. Budget-justification contract funding, not obligations.

Where FY2027 funding flowsShare$M
Other / unspecified100%5.5
FY2027 request100%5.5
Program detail

Mission & acquisition strategy

Project 593, Joint Battle Command - Platform (JBC-P) FY 2026 funding was realigned to PE 0604818A / Army Tactical Command & Control Hardware & Software, Projects EJ6 and EK9, in support of in support of the Army's NGC2 initiative to modernize C2 systems, for the Data and Application Layers. The capability being developed under this project remains critical and relevant to the Warfighter. This capability, along with its resources and requirement will transition under the overarching NGC2 capability to eliminate stove-piping, reduce duplication of effort, and provide capability within a single NGC2 core architecture.

The CMOSS Mounted Form Factor (CMFF) Mounted Common Infrastructure (MCI) Chassis program responds to Army requirements in the approved CMFF Abbreviated Capability Development Document (A-CDD), validated on 4 January 2021, and is pursuing a Middle Tier of Acquisition (MTA) Rapid Prototyping (RP) acquisition pathway, which was initiated in FY2025. The MTA RP effort spans five years and will prototype the chassis and software that manages the operation of the chassis, as well as integrate the capability cards and peripheral enabling devices, assuring the integrated solution operates as required.

Project DL9, DH4, DH5 — APNT Cards C5ISR Mounted Form Factor (CMFF)
  • Management Services
  • Product Development
  • Support
  • Test and Evaluation
Ask Hitch

Ask this program element

Answers are generated from the figures on this page — the FY2027 justification exhibits and the marks tracked above — and nothing else is consulted. Confirm any figure against the cited exhibit before you use it externally.

H
Questions this page can answer
How does the FY2027 request compare with FY2026, and what does the five-year plan show?What did the FY2027 NDAA committees do to this request?Which project inside PE 0604805A is growing fastest, and which is shrinking?How is the FY2027 request split between industry and government performers?

This page carries the budget justification and the NDAA marks — nothing else. For what a contractor has actually been obligated, the ledger is at hitchintel.com/vendors; for live solicitations, hitchintel.com/opportunities. Both are member surfaces.

Provenance

Cite this page

Sources
FY2027 Department of the Army RDT&E Budget Justification · Exhibits R-2 / R-3 · PE 0604805A (President's Budget PB2027) — and FY2027 NDAA committee marks, as tracked 2026-07-27.
Suggested citation
HitchAI, "Command, Control, Communications Systems - Eng Dev (PE 0604805A)," federal budget intelligence, PB2027 vintage. hitchintel.com/programs/0604805A
Machine access
Markdown twin /programs/0604805A.md · MCP mcp.hitchintel.combudget_get_program_element, budget_get_cong_marks
FY2027 Request
$5.5M
▲ 3.3% vs FY2026
FY2026 Enacted
$5.4M
In law

APNT Cards C5ISR Mounted Form Factor (CMFF) — one RDT&E project inside PE 0604805A. Congressional marks are recorded on the program element, not on a project.

Project DL9 — APNT Cards C5ISR Mounted Form Factor (CMFF) — requests $5.5M in FY2027, 100% of the $5.5M requested for program element 0604805A. Year over year it grows 3.3% against FY2026.

Funding trajectory

Project DL9 funding, FY2026–FY2031

Prior years are actuals, the budget year is the request, and the outyears are the FYDP plan. Estimate types are colored and never summed into one figure. Projects carry the full five-year plan; the activities inside them stop at the budget year.

05.4FY26ENACTED5.5FY27REQUEST6.0FY285.2FY295.2FY305.2FY31
Enacted Request Outyear (FYDP)
Fiscal YearEstimate TypeAmount ($M)
FY2026Enacted5.4
FY2027Request5.5
FY2028Outyear6.0
FY2029Outyear5.2
FY2030Outyear5.2
FY2031Outyear5.2
Inside the project

1 accomplishment / planned program

The R-2A exhibit. Activities carry the prior, current and budget year only — no five-year plan — and they are descriptive: coverage is partial and they do not always add back to the project, so count them, never total them.

CMFF APNT Cards▲ 3%
FY2025 actual
FY2026 enacted$5.4M
FY2027 request$5.5M

FY2027 planned work The Fiscal Year (FY) 2027 funds in the amount of $5.541 million to continue the CMFF APNT Card prototype development, testing, and integration engineering support into the CMFF Mounted Common Infrastructure Chassis.

FY2026 to FY2027 change Funding increase due to an economic adjustment.

FY2026 plans — current year Fiscal Year (FY) 2026 funds in the amount of $5.365 million continues the CMFF APNT Card prototype integration engineering support into the CMFF Mounted Common Infrastructure Chassis, initiates prototype hardware and software development, and prototype developmental testing efforts.

Project detail

What project DL9 buys

The CMFF APNT Card provides the solutions required by the CMFF Abbreviated Capability Development Document and distributes APNT data to payloads within the CMFF chassis and external systems as needed. The CMFF APNT card provides assured PNT by utilizing multiple PNT sources and leveraging multiple open architectures. The CMFF APNT Card prototyping, and software development will be conducted in accordance with Modular Open Systems Approach (MOSA) (Reference House Report 116-442, 2020). The CMFF APNT Card complies with the PNT Reference Architecture and MOSA compliant hardware; CMOSS and software frameworks (PNT Operating System (pntOS)), to ensure a plug and play capability with M-Code and Alternative Navigation (ALTNAV). The Fiscal Year (FY) 2027 funds in the amount of $5.541 million to continue the CMFF APNT Card prototype development, testing, and integration engineering support into the CMFF Mounted Common Infrastructure Chassis.

R-3 lines of work
  • Management Services
  • Product Development
  • Support
  • Test and Evaluation
FY2027 Request
$0.0M
▼ 100% vs FY2026
FY2026 Enacted
$30.9M
▲ 47% vs FY2025
FY2025 Actual
$21.0M
Prior year

CMOSS Mounted Form Factor (CMFF) Radio Cards — one RDT&E project inside PE 0604805A. Congressional marks are recorded on the program element, not on a project.

Project DH4 — CMOSS Mounted Form Factor (CMFF) Radio Cards — requests in FY2027, 0.0% of the $5.5M requested for program element 0604805A. Year over year it falls 100% against FY2026.

Funding trajectory

Project DH4 funding, FY2025–FY2026

Prior years are actuals, the budget year is the request, and the outyears are the FYDP plan. Estimate types are colored and never summed into one figure. Projects carry the full five-year plan; the activities inside them stop at the budget year.

25021.0FY25ACTUAL30.9FY26ENACTED
Actual Enacted
Fiscal YearEstimate TypeAmount ($M)
FY2025Actual21.0
FY2026Enacted30.9
Inside the project

3 accomplishments / planned programs

The R-2A exhibit. Activities carry the prior, current and budget year only — no five-year plan — and they are descriptive: coverage is partial and they do not always add back to the project, so count them, never total them. Opening lines only here — the full year-by-year narrative is on the project page.

Program Management Support▼ 100%
FY2025 actual$0.8M
FY2026 enacted$4.8M
FY2027 request

FY 2025 Research Development Test & Evaluation (RDT&E) funds Matrix and contractor support to assist with the CMFF program development, testing, integration and evaluation and program oversight.

Product Development▼ 100%
FY2025 actual$20.2M
FY2026 enacted$25.0M
FY2027 request

FY 2025 Research Development Test & Evaluation (RDT&E) funding will support prototyping contracts with vendors and provide technical systems engineering support for Hardware & Software development of the SDR card, CSS card, DRH and Victory Audio Adapter.

Test and Evaluation▼ 100%
FY2025 actual
FY2026 enacted$1.2M
FY2027 request

FY 2026 Research Development Test & Evaluation (RDT&E) funding supports CMFF integration, testing, and evaluation of the Software Defined Radio (SDR) cards, Cryptographic Subsystem (CSS) cards, Digital Radio Heads and support from the Crypto Mod lab, Open Innovation Lab (OIL), and Prototype Integration Facility (PIF). As well as multiple…

Project DH4 — every activity in full →
Project detail

What project DH4 buys

Command, Control, Communications, Computers, Cyber, Intelligence, Surveillance and Reconnaissance (C5ISR) Modular Open Suite of Standards (CMOSS) Mounted Form Factor (CMFF) Radio Card Mid-Tier Acquisition (MTA) Rapid Prototype (RP) program delivers Software Defined Radio (SDR) cards, Cryptographic Subsystem (CSS) cards, Digital Radio Heads (DRH) and Victory Audio Adapter (VAX) required by the CMOSS Mounted Form Factor (CMFF) Abbreviated Capability Development Document (A-CDD) for the Ground and Aviation's tactical communication requirements utilizing an Other Transaction Authority(OTA) contracting strategy. CMFF Radio Cards provide simultaneous transmission and reception of multiple waveforms across multiple channels in a single or multiple SDR card(s) integrated in the CMFF chassis with NSA certifiable CSS and interoperable with the Digital Radio Head. CMFF Radio cards initial capability development includes but is not limited to Single Channel Ground and Airborne Radio System (SINCGARS), Air Traffic Control (ATC), Warrior Robust Enhanced Network (WREN) and future advanced networking waveforms; initial Cryptographic Subsystem Card (CSS), Digital Radio Head (DRH), and Victory Audio Adapter (VAX). Advanced capability development includes but is not limited to Mobile User Objective System (MUOS), Link-16, High Frequency (HF), HAVEQUICK (HQ), Second generation Anti-jam Tactical UHF Radio for NATO (SATURN), Demand Assigned Multiple Access (DAMA) and future advanced networking waveforms; and final CSS, DRH and VAX. The total cost of the CMFF RC Middle Tier of Acquisition (MTA) effort is $96.1 million RDT&E from FY25 to FY29. FY2027 funding supports Hardware and Software Development (SDR card, CSS card, Digital Radiohead and Victory Audio Adapter), Test, Integration and Evaluation, and Program Management Support. This funding directly supports the Army's Next Generation Command and Control (NGC2) initiative, specifically targeting the modernization of the Command and Control (C2) Transport Layer. The C5ISR Modular Open Suite of Standards (CMOSS) Mounted Form Factor (CMFF) is a cornerstone of this effort, embodying the key tenets of NGC2 to deliver a more agile, interoperable, and data-centric communications backbone for ground and aviation platforms.

R-3 lines of work
  • Management Services
  • Product Development
  • Test and Evaluation
FY2027 Request
$0.0M
▼ 100% vs FY2026
FY2026 Enacted
$27.4M
▼ 24% vs FY2025
FY2025 Actual
$36.0M
Prior year

CMOSS Mounted Form Factor (CMFF) Chassis — one RDT&E project inside PE 0604805A. Congressional marks are recorded on the program element, not on a project.

Project DH5 — CMOSS Mounted Form Factor (CMFF) Chassis — requests in FY2027, 0.0% of the $5.5M requested for program element 0604805A. Year over year it falls 100% against FY2026.

Funding trajectory

Project DH5 funding, FY2025–FY2026

Prior years are actuals, the budget year is the request, and the outyears are the FYDP plan. Estimate types are colored and never summed into one figure. Projects carry the full five-year plan; the activities inside them stop at the budget year.

25036.0FY25ACTUAL27.4FY26ENACTED
Actual Enacted
Fiscal YearEstimate TypeAmount ($M)
FY2025Actual36.0
FY2026Enacted27.4
Inside the project

3 accomplishments / planned programs

The R-2A exhibit. Activities carry the prior, current and budget year only — no five-year plan — and they are descriptive: coverage is partial and they do not always add back to the project, so count them, never total them. Opening lines only here — the full year-by-year narrative is on the project page.

CMFF - Product Development▼ 100%
FY2025 actual$32.5M
FY2026 enacted$19.8M
FY2027 request

Funding supports a multi-vendor OTA award, including prototyping, hardware and software development, and lab-asset procurement for experimentation on ground platforms and technical studies and maturation on aviation platforms.

CMFF - Test and Evaluation▼ 100%
FY2025 actual$0.8M
FY2026 enacted$4.7M
FY2027 request

Funding supports demonstration and integration testing, software defined testbed development, and the kickoff of National Security Agency (NSA) evaluation activities for CMFF MCI Chassis Block 1.

CMFF - Program Management Support▼ 100%
FY2025 actual$2.8M
FY2026 enacted$3.0M
FY2027 request

Funding provides the development, systems engineering, technical and business Matrix and Contractor personnel to support the CMFF MCI Chassis program efforts.

Project DH5 — every activity in full →
Project detail

What project DH5 buys

This funding supports the Army's Next Generation Command and Control (NGC2) initiative to modernize Command and Control (C2) systems, Infrastructure Layer. Command, Control, Communications, Computers, Cyber, Intelligence, Surveillance and Reconnaissance (C5ISR) Modular Open Suite of Standards (CMOSS) is a defined suite of open architecture and Army standards that facilitate the reduction of system size, weight, and power-cooling (SWaP-C) and ensure commonality across multiple vehicles and platforms. Sharing of hardware and software components is enabled within the CMFF Mounted Common Infrastructure (MCI) Chassis, which will help move the implementation of C5ISR/Electronic Warfare (C5ISR/EW) capabilities away from costly and complex separate "stove-piped boxes" onto individual platforms. The use of open standards will make it simpler and more cost-effective to upgrade capabilities and/or keep pace with commercial technology by eliminating complex integration challenges and proprietary interfaces. The CMFF capability can only be realized when paired with the development of associated capability cards for integration into the chassis and peripheral enabling devices, such as antennae and appropriate user interfaces. Other programs are responsible for funding and developing the capability cards and peripheral devices; the CMFF MCI Chassis program is responsible for chassis development, system of system integration of capability cards and external resources into the chassis and platform integration.

R-3 lines of work
  • Management Services
  • Product Development
  • Test and Evaluation