Roll-up of 2 projects. Projects are the summable leaves — the PE total is their sum, never added to it.
For fiscal year 2027, the U.S. Space Force is requesting $10.5M for Space Innovation, Integration and Rapid Technology Development under RDT&E program element 1203174SF, down 87% from FY2026.
Funding profile, FY2025–FY2031
Prior years are actuals, the budget year is the request, and the outyears are the FYDP plan. Estimate types are colored and never summed into one figure.
| Fiscal Year | Estimate Type | Amount ($M) |
|---|---|---|
| FY2025 | Actual | 47.2 |
| FY2026 | Enacted | 81.0 |
| FY2027 | Request | 10.5 |
| FY2028 | Outyear | 10.9 |
| FY2029 | Outyear | 11.1 |
| FY2030 | Outyear | 11.3 |
| FY2031 | Outyear | 11.5 |
Acquisition lifecycle
This program is funded in RDT&E Budget Activity 7 — Operational System Development.
2 projects roll up into PE 1203174SF
Projects are the summable leaves — the PE total is their sum, never added to it. Program elements and projects carry the full five-year plan; activities stop at the budget year. This PE moves -87% overall, which can hide much larger swings below.
Enterprise Training Services Development
Congressional marks
Committee marks on the FY2027 request. Adds and cuts are reconciled in conference before they become law.
Where the FY2027 request goes
Performers named in the R-3 exhibit, resolved into industry, government-lab, and unspecified shares. Budget-justification contract funding, not obligations.
| Where FY2027 funding flows | Share | $M |
|---|---|---|
| Industry primes | 100% | 10.5 |
| FY2027 request | 100% | 10.5 |
Mission & acquisition strategy
The Space Innovation, Integration, and Rapid Technology Development (SIIRTD) program element delivers enterprise capabilities and solutions to field combat-ready forces and ensure space domain superiority in an evolving threat environment. Enterprise Training Services Development (ETSD) delivers operationally realistic space combat training capabilities via a system-of-systems architecture to generate, assess, and sustain Guardian lethality. Capabilities developed are in accordance with the USSF Operational Test and Training Infrastructure (OTTI) Strategic Requirements Document (SRD) and Space Training and Readiness Command and Space Operations Command requirements and priorities.
FY26 and 27 activities are executed via existing contracts and Interagency Agreements. Contracts are both competitively awarded and sole sourced (in accordance with Small Business Innovative Research Policy Directive, May 2023). These contracts and Interagency Agreements allow for immediate execution of all FY26 and 27 funds with minimal contracting actions required to ensure continuity of effort across the FYs.
- Product Development
Ask this program element
Answers are generated from the figures on this page — the FY2027 justification exhibits and the marks tracked above — and nothing else is consulted. Confirm any figure against the cited exhibit before you use it externally.
This page carries the budget justification and the NDAA marks — nothing else. For what KBR has actually been obligated, the ledger is at hitchintel.com/vendors; for live solicitations, hitchintel.com/opportunities. Both are member surfaces.
Cite this page
/programs/1203174SF.md · MCP mcp.hitchintel.com → budget_get_program_element, budget_get_cong_marksSpace Analysis and Application Development — one RDT&E project inside PE 1203174SF. Congressional marks are recorded on the program element, not on a project.
Project 67A011 — Space Analysis and Application Development — requests $10.5M in FY2027, 100% of the $10.5M requested for program element 1203174SF. Year over year it grows 4.7% against FY2026.
Project 67A011 funding, FY2025–FY2031
Prior years are actuals, the budget year is the request, and the outyears are the FYDP plan. Estimate types are colored and never summed into one figure. Projects carry the full five-year plan; the activities inside them stop at the budget year.
| Fiscal Year | Estimate Type | Amount ($M) |
|---|---|---|
| FY2025 | Actual | 9.7 |
| FY2026 | Enacted | 10.1 |
| FY2027 | Request | 10.5 |
| FY2028 | Outyear | 10.9 |
| FY2029 | Outyear | 11.1 |
| FY2030 | Outyear | 11.3 |
| FY2031 | Outyear | 11.5 |
1 accomplishment / planned program
The R-2A exhibit. Activities carry the prior, current and budget year only — no five-year plan — and they are descriptive: coverage is partial and they do not always add back to the project, so count them, never total them. Opening lines only here — the full year-by-year narrative is on the project page.
Continue supporting the SpOC field command to provide data-driven recommendations and solutions that drive assessment strategy development and analysis for contingency planned force structure for the USSF. The funds will also support space capability development and increase strategic responsiveness with quick-turn senior leader ops…
Read the FY2027 plan →Named performers on project 67A011
Performers named in the R-3 exhibit under this project. Share is of the project's whole FY2027 R-3 total — the same denominator the program-element split uses, so the two read on one scale and will not sum to 100% when unnamed or government work is in the mix. Budget-justification contract funding, not obligations.
What project 67A011 buys
Located at Peterson SFB, Colorado, the Space Innovation, Integration, and Rapid Technology Development (SIIRTD) program develops and modifies modeling and simulation tools that USSF/Space Operations Command uses for operations research, military utility analyses, tradeoff studies, verification and validation, and other assessments of space mission areas to guide SPAFORGEN, Space Domain Awareness (SDA), readiness, and other activities. SIIRTD projects respond to changes - both existing and projected - in space operations, technology, and threats to ensure space operators are provided accurate and relevant data and capabilities. SIIRTD tools and analyses enable USSF and joint warfighters to execute their missions more efficiently. Efforts within the space warfighting enterprise are evaluating ways to increase innovation and resiliency, aiming to reduce risk, repurpose existing capabilities, integrate new capabilities, and prototype and field combat efficiencies and automations via all appropriate acquisition authorities and contract mechanisms.
- Product Development
Enterprise Training Services Development — one RDT&E project inside PE 1203174SF. Congressional marks are recorded on the program element, not on a project.
Project 674671 — Enterprise Training Services Development — requests $0.0M in FY2027, 0.0% of the $10.5M requested for program element 1203174SF. Year over year it falls 100% against FY2026.
Project 674671 funding, FY2025–FY2031
Prior years are actuals, the budget year is the request, and the outyears are the FYDP plan. Estimate types are colored and never summed into one figure. Projects carry the full five-year plan; the activities inside them stop at the budget year.
| Fiscal Year | Estimate Type | Amount ($M) |
|---|---|---|
| FY2025 | Actual | 37.5 |
| FY2026 | Enacted | 71.0 |
| FY2027 | Request | 0.0 |
| FY2028 | Outyear | 0.0 |
| FY2029 | Outyear | 0.0 |
| FY2030 | Outyear | 0.0 |
| FY2031 | Outyear | 0.0 |
1 accomplishment / planned program
The R-2A exhibit. Activities carry the prior, current and budget year only — no five-year plan — and they are descriptive: coverage is partial and they do not always add back to the project, so count them, never total them. Opening lines only here — the full year-by-year narrative is on the project page.
N/A. Beginning in FY 2027, funding is moved into new Program Element 1206617SF, Project 644441, Operational Test & Training Infrastructure.
What project 674671 buys
Enterprise Training Services Development (ETSD) builds combat-ready forces by delivering enterprise training capabilities in alignment with the OTTI SRD. ETSD capabilities enable Guardians to train and develop tactics in an operationally relevant synthetic environment. Capabilities are delivered via technology such as: - mission-specific simulators for weapons system operations training and threat/scenario-driven training and tactics development - threat-representative models of adversary capabilities - synthetic, physics-based digital environments capable of conducting multi-mission and multi-user full-force distributed combat training and exercises - artificial intelligence to augment Guardians playing aggressor roles in training and exercise scenarios - synthetic environment visualizations and friendly/adversary/integrated operational pictures - networks and computer hardware required to deliver the above capabilities and interoperate with other joint acquisition, test, training, exercise, and exercise platforms and tools Activities may include, but are not limited to program office support, studies, technical analysis, experimentation, risk reduction, prototyping, and activities that may leverage commercial, U.S. Government partnership, and international opportunities to respond to existing and emerging adversarial threats with speed and agility. Beginning in FY 2027, Project 674671, Enterprise Training Services Development, is moved into new Program Element 1206617SF, Operational Test & Training Infrastructure, Project 644441, Operational Test & Training Infrastructure.
- Product Development
- Management Services