Roll-up of 3 projects. Projects are the summable leaves — the PE total is their sum, never added to it.
For fiscal year 2027, the U.S. Air Force is requesting $733.2M for ICBM Reentry Vehicles under RDT&E program element 0101328F, up 186% over FY2026. In the FY2027 defense authorization, House approps moved to cut it to $657.8M.
Funding profile, FY2025–FY2031
Prior years are actuals, the budget year is the request, and the outyears are the FYDP plan. Estimate types are colored and never summed into one figure.
| Fiscal Year | Estimate Type | Amount ($M) |
|---|---|---|
| FY2025 | Actual | 379.0 |
| FY2026 | Enacted | 256.8 |
| FY2027 | Request | 733.2 |
| FY2028 | Outyear | 1,053.3 |
| FY2029 | Outyear | 1,152.0 |
| FY2030 | Outyear | 1,484.1 |
| FY2031 | Outyear | 1,362.8 |
Acquisition lifecycle
This program is funded in RDT&E Budget Activity 7 — Operational System Development.
3 projects roll up into PE 0101328F
Projects are the summable leaves — the PE total is their sum, never added to it. Program elements and projects carry the full five-year plan; activities stop at the budget year. This PE moves 186% overall, which can hide much larger swings below.
Next Generation Reentry Vehicle (NGRV)
Advanced Capabilities for Missile Enhancement (ACME)
ACME is funded on 2 lines across 2 appropriations
This page shows $51.2M of ACME, 100% of the program's $51.2M FY2027 request. The rest is appropriated elsewhere.
| Also funded here | Type | Component | FY2027 $M |
|---|---|---|---|
| Allied/Coalition Maritime Environment (ACME) | RDT&E | Navy | 0.0 |
| ACME total | Air Force, Navy | 51.2 |
Lines whose title names the program. 1 further lines only mention ACME in their justification text — those fund something else and are deliberately excluded from the total.
The request is contested
Committee marks on the FY2027 request. Adds and cuts are reconciled in conference before they become law.
Where the FY2027 request goes
Performers named in the R-3 exhibit, resolved into industry, government-lab, and unspecified shares. Budget-justification contract funding, not obligations.
| Where FY2027 funding flows | Share | $M |
|---|---|---|
| Industry primes | 66% | 485.5 |
| Government labs & warfare centers | 2.2% | 15.8 |
| Other / unspecified | 32% | 231.9 |
| FY2027 request | 100% | 733.2 |
Mission & acquisition strategy
The Intercontinental Ballistic Missile (ICBM) Reentry Vehicles (RVs) activity will design, develop, produce, and deploy advanced countermeasures and integrated RV systems capable of delivering the W87-1 warhead and future warheads when released from ICBM weapon systems. The Mk21A program will meet the requirements laid out in the LGM-35A Sentinel weapon system Capability Development Document (CDD) as directed by Air Force Global Strike Command and will provide needed performance and security enhancements over the Mk21 RV to meet the upgraded requirements for the Department of Energy (DOE)/ National Nuclear Security Administration (NNSA) W87-1 warhead.
The Mk21A RV program acquisition strategy delivers an integrated RV capable of delivering the W87-1 warhead. For the EMD phase, the Program Office awarded a sole-source cost plus incentive/award fee contract in October 2023. The Air Force is responsible for developing, producing, and maintaining the RV. The DOE/NNSA develops/modifies the nuclear weapon inside the RV, including the Weapon Electrical System, which is the firing set that interfaces with the DoW fuze. Mk21A includes the use of Mk21 Mod 6 aeroshells which were originally developed as test vehicles for the legacy Peacekeeper ICBM and must be modified for use as war reserve aeroshells.
- Product Development
- Support
- Test and Evaluation
- Management Services
Ask this program element
Answers are generated from the figures on this page — the FY2027 justification exhibits and the marks tracked above — and nothing else is consulted. Confirm any figure against the cited exhibit before you use it externally.
This page carries the budget justification and the NDAA marks — nothing else. For what Lockheed Martin has actually been obligated, the ledger is at hitchintel.com/vendors; for live solicitations, hitchintel.com/opportunities. Both are member surfaces.
Cite this page
/programs/0101328F.md · MCP mcp.hitchintel.com → budget_get_program_element, budget_get_cong_marksMk21A Reentry Vehicle — one RDT&E project inside PE 0101328F. Congressional marks are recorded on the program element, not on a project.
Project 674920 — Mk21A Reentry Vehicle — requests $539.8M in FY2027, 74% of the $733.2M requested for program element 0101328F. Year over year it grows 161% against FY2026.
Project 674920 funding, FY2025–FY2031
Prior years are actuals, the budget year is the request, and the outyears are the FYDP plan. Estimate types are colored and never summed into one figure. Projects carry the full five-year plan; the activities inside them stop at the budget year.
| Fiscal Year | Estimate Type | Amount ($M) |
|---|---|---|
| FY2025 | Actual | 362.9 |
| FY2026 | Enacted | 206.9 |
| FY2027 | Request | 539.8 |
| FY2028 | Outyear | 511.4 |
| FY2029 | Outyear | 416.8 |
| FY2030 | Outyear | 409.8 |
| FY2031 | Outyear | 460.1 |
1 accomplishment / planned program
The R-2A exhibit. Activities carry the prior, current and budget year only — no five-year plan — and they are descriptive: coverage is partial and they do not always add back to the project, so count them, never total them. Opening lines only here — the full year-by-year narrative is on the project page.
• Continue to execute EMD contract to continue advancing Mk21A major activities to include systems engineering activities, information technology, data management, analytical capabilities and delivery of mature, low risk reentry vehicle design. • Continue to develop the critical design review for RV hardware. • Increase efforts to…
Read the FY2027 plan →Named performers on project 674920
Performers named in the R-3 exhibit under this project. Share is of the project's whole FY2027 R-3 total — the same denominator the program-element split uses, so the two read on one scale and will not sum to 100% when unnamed or government work is in the mix. Budget-justification contract funding, not obligations.
What project 674920 buys
The Mk21A Reentry Vehicle (RV) program will design, develop, produce, and deploy an integrated RV capable of delivering the W87-1 warhead when released from the LGM-35A Sentinel weapon system. The Mk21A program will provide needed performance and security enhancements over the Mk21 RV to meet the upgraded requirements for the Department of Energy (DOE)/ National Nuclear Security Administration (NNSA) W87-1 warhead, while ensuring the time certain delivery of both the W87-1 and Mk21A programs. The Mk21A will also meet the requirements laid out in the LGM-35A Sentinel weapon system Capability Development Document (CDD) as directed by Air Force Global Strike Command. The Mk21A RV includes: shape-stable nose tip; high-impulse transducer; arming and fuzing subsystem (AFS); aeroshell forward section, body section, and rear cover; radio frequency subsystem with antennas; RV spin subsystem; in-flight disconnect cable; and other electrical cables. During the Engineering and Manufacturing Development (EMD) phase, the Mk21A program will include prime contractor development of a critical RV design, applicable support equipment, data, flight test hardware, infrastructure, and training materials while examining and mitigating weapon system integration risks, nuclear surety, hardness and certification, and system vulnerability assessments. Additionally, the program, in conjunction with the DOE/NNSA, will develop test assets to ensure the integration and qualification of the Mk21A and W87-1 on the LGM-35A Sentinel weapon system. This program element may include necessary civilian pay expenses required to manage, execute, and deliver weapon system capability. The use of such program funds would be in addition to the civilian pay expenses budgeted in program elements 0605827F, 0605828F, 0605829F, 0605831F, 0605832F, 0605833F, 0605898F, and 0606398F.
- Product Development
- Support
- Test and Evaluation
- Management Services
Next Generation Reentry Vehicle (NGRV) — one RDT&E project inside PE 0101328F. Congressional marks are recorded on the program element, not on a project.
Project 675921 — Next Generation Reentry Vehicle (NGRV) — requests $142.1M in FY2027, 19% of the $733.2M requested for program element 0101328F. It is a new start — no prior-year or current-year money.
Project 675921 funding, FY2025–FY2031
Prior years are actuals, the budget year is the request, and the outyears are the FYDP plan. Estimate types are colored and never summed into one figure. Projects carry the full five-year plan; the activities inside them stop at the budget year.
| Fiscal Year | Estimate Type | Amount ($M) |
|---|---|---|
| FY2025 | Actual | 0.0 |
| FY2026 | Enacted | 0.0 |
| FY2027 | Request | 142.1 |
| FY2028 | Outyear | 453.9 |
| FY2029 | Outyear | 633.2 |
| FY2030 | Outyear | 970.4 |
| FY2031 | Outyear | 796.7 |
1 accomplishment / planned program
The R-2A exhibit. Activities carry the prior, current and budget year only — no five-year plan — and they are descriptive: coverage is partial and they do not always add back to the project, so count them, never total them. Opening lines only here — the full year-by-year narrative is on the project page.
• Expand concept exploration for integration studies • Build digital models and prototypes • Mature RV technologies • Explore countermeasure technologies
Read the FY2027 plan →What project 675921 buys
The Next Generation Reentry Vehicle (NGRV) program will design, develop, produce, and deploy new payload system suites (reentry vehicles and countermeasures) and integrate them into ICBM weapon systems. Key next generation payload attributes include enhancements in accuracy and lethality. NGRV and associated advanced countermeasure capabilities are based on emerging threats, warfighter priorities, and development capacity. Program activities will also include the employment of digital acquisitions through the application of digital engineering, agile software development, and open systems architectures. The NGRV program will leverage investments by the ICBM Demonstration/Validation program, the Science & Technology community, and Navy reentry systems application program. In FY2026 NGRV efforts were accomplished under BPAC 675920 Next Generation Reentry Capabilities. In FY2027 NGRV BPAC (675921) was created, providing further visibility and traceability. FY2027 funding supports early acquisition activities that lead to competitive contract awards for NGRV development. NGRV will develop digital models and perform early prototyping to prepare for acquisition activities and to strengthen the atrophied industrial base, posturing the nation to counter adversary threats both projected and unforeseen. This strategy enables a diverse pool of vendors to contribute to the development of materiel solutions, which support mission requirements that combat future and immediate threats to drive ultimate effectiveness requirements for the weapon system. This funding includes program management support, operational concept exploration, technology trade studies, operational and system architecture development, maturation and risk reduction of RV/countermeasure-related technologies, including weapons system and integrated system concept development/demonstration.
- Product Development
Advanced Capabilities for Missile Enhancement (ACME) — one RDT&E project inside PE 0101328F. Congressional marks are recorded on the program element, not on a project.
Project 675920 — Advanced Capabilities for Missile Enhancement (ACME) — requests $51.2M in FY2027, 7.0% of the $733.2M requested for program element 0101328F. Year over year it grows 2.7% against FY2026.
Project 675920 funding, FY2025–FY2031
Prior years are actuals, the budget year is the request, and the outyears are the FYDP plan. Estimate types are colored and never summed into one figure. Projects carry the full five-year plan; the activities inside them stop at the budget year.
| Fiscal Year | Estimate Type | Amount ($M) |
|---|---|---|
| FY2025 | Actual | 16.1 |
| FY2026 | Enacted | 49.9 |
| FY2027 | Request | 51.2 |
| FY2028 | Outyear | 88.0 |
| FY2029 | Outyear | 102.0 |
| FY2030 | Outyear | 103.9 |
| FY2031 | Outyear | 106.0 |
1 accomplishment / planned program
The R-2A exhibit. Activities carry the prior, current and budget year only — no five-year plan — and they are descriptive: coverage is partial and they do not always add back to the project, so count them, never total them. Opening lines only here — the full year-by-year narrative is on the project page.
• Award contract to Prime to develop ICBM capabilities. More details are available at higher classification levels.
Named performers on project 675920
Performers named in the R-3 exhibit under this project. Share is of the project's whole FY2027 R-3 total — the same denominator the program-element split uses, so the two read on one scale and will not sum to 100% when unnamed or government work is in the mix. Budget-justification contract funding, not obligations.
What project 675920 buys
The Advanced Capabilities for Missile Enhancement (ACME) program supports enhancements to ICBM operations. More information is available at higher classification levels. In FY2026, BPAC 675920, Next Generation Reentry Capabilities (NGRC) encompassed efforts to design, develop, produce, and deploy new payload system suites (reentry vehicles and/or capabilities) In FY2027, BPAC 675920 was renamed Advanced Capability for Missile Enhancement (ACME) NGRC funding stayed within BPAC 675920. FY2027 continues to support the enabling functions of ACME to include but is not limited to Prime support and studies, engineering support, security support, direct program support costs and information technology. This program element may include necessary civilian pay expenses required to manage, execute, and deliver weapon system capability. The use of such program funds would be in addition to the civilian pay expenses budgeted in program element 0605827F, 0605828F, 0605829F, 0605831F, 0605832F, 0605833F, 0605898F, 0606398F.
- Product Development
- Support
- Test and Evaluation
- Management Services