Roll-up of 2 projects. Projects are the summable leaves — the PE total is their sum, never added to it.
For fiscal year 2027, the U.S. Navy is requesting $212.0M for FRIGATE Development under RDT&E program element 0603599N, up 161% over FY2026.
Funding profile, FY2025–FY2031
Prior years are actuals, the budget year is the request, and the outyears are the FYDP plan. Estimate types are colored and never summed into one figure.
| Fiscal Year | Estimate Type | Amount ($M) |
|---|---|---|
| FY2025 | Actual | 103.2 |
| FY2026 | Enacted | 81.2 |
| FY2027 | Request | 212.0 |
| FY2028 | Outyear | 247.6 |
| FY2029 | Outyear | 193.7 |
| FY2030 | Outyear | 197.3 |
| FY2031 | Outyear | 195.6 |
Acquisition lifecycle
This program is funded in RDT&E Budget Activity 4 — Advanced Component Development & Prototypes.
2 projects roll up into PE 0603599N
Projects are the summable leaves — the PE total is their sum, never added to it. Program elements and projects carry the full five-year plan; activities stop at the budget year. This PE moves 161% overall, which can hide much larger swings below.
Frigate
Congressional marks
Committee marks on the FY2027 request. Adds and cuts are reconciled in conference before they become law.
Where the FY2027 request goes
Performers named in the R-3 exhibit, resolved into industry, government-lab, and unspecified shares. Budget-justification contract funding, not obligations.
| Where FY2027 funding flows | Share | $M |
|---|---|---|
| Industry primes | 14% | 29.0 |
| Government labs & warfare centers | 43% | 90.3 |
| Other / unspecified | 44% | 92.8 |
| FY2027 request | 100% | 212.0 |
Mission & acquisition strategy
The FF(X) Frigate is a strategic necessity to close a significant shortfall in the Navy's small surface combatant inventory and to build a more balanced, flexible fleet. Frigate directly supports the 2025 National Security Strategy which calls for, "A more suitable Navy presence to control sea lanes, to thwart illegal and other unwanted migration, to reduce human and drug trafficking, and to control key transit routes in a crisis". FF(X) will be a vanguard of the Navy's Hedge Strategy, within the General-Purpose Force handling routine missions across the globe and freeing the Main Battle Force to remain focused on high-end combat.
The FF(X) Class acquisition strategy was approved by ASN RD&A on 8 Dec 2025.
- Product Development
- Support
- Test and Evaluation
- Management Services
Ask this program element
Answers are generated from the figures on this page — the FY2027 justification exhibits and the marks tracked above — and nothing else is consulted. Confirm any figure against the cited exhibit before you use it externally.
This page carries the budget justification and the NDAA marks — nothing else. For what Contractors has actually been obligated, the ledger is at hitchintel.com/vendors; for live solicitations, hitchintel.com/opportunities. Both are member surfaces.
Cite this page
/programs/0603599N.md · MCP mcp.hitchintel.com → budget_get_program_element, budget_get_cong_marksFF(X) — one RDT&E project inside PE 0603599N. Congressional marks are recorded on the program element, not on a project.
Project 3085 — FF(X) — requests $212.0M in FY2027, 100% of the $212.0M requested for program element 0603599N. Year over year it grows 161% against FY2026.
Project 3085 funding, FY2025–FY2031
Prior years are actuals, the budget year is the request, and the outyears are the FYDP plan. Estimate types are colored and never summed into one figure. Projects carry the full five-year plan; the activities inside them stop at the budget year.
| Fiscal Year | Estimate Type | Amount ($M) |
|---|---|---|
| FY2025 | Actual | 0.0 |
| FY2026 | Enacted | 81.2 |
| FY2027 | Request | 212.0 |
| FY2028 | Outyear | 247.6 |
| FY2029 | Outyear | 193.7 |
| FY2030 | Outyear | 197.3 |
| FY2031 | Outyear | 195.6 |
2 accomplishments / planned programs
The R-2A exhibit. Activities carry the prior, current and budget year only — no five-year plan — and they are descriptive: coverage is partial and they do not always add back to the project, so count them, never total them. Opening lines only here — the full year-by-year narrative is on the project page.
Continue systems engineering and platform integration efforts for C4I, Combat, and Aviation systems. Begin System Qualification Testing (SQT) of the Combat Management System (CMS) and initiate Combat System Integration (CSI) Testing to verify system functionality, interoperability, and readiness for integration into the total ship combat…
Read the FY2027 plan →Execute live-fire tests in support of generating empirical LFT&E survivability data for verification, validation, and accreditation of multiple LFT&E survivability models. Conduct Cyber Range testing to assess system performance in a representative operational cyber environment and to validate the system's ability to operate securely…
Read the FY2027 plan →Named performers on project 3085
Performers named in the R-3 exhibit under this project. Share is of the project's whole FY2027 R-3 total — the same denominator the program-element split uses, so the two read on one scale and will not sum to 100% when unnamed or government work is in the mix. Budget-justification contract funding, not obligations.
What project 3085 buys
The FF(X) Frigate is a strategic necessity to close a significant shortfall in the Navy's small surface combatant inventory and to build a more balanced, flexible fleet. Frigate directly supports the 2025 National Security Strategy which calls for, "A more suitable Navy presence to control sea lanes, to thwart illegal and other unwanted migration, to reduce human and drug trafficking, and to control key transit routes in a crisis". FF(X) will be a vanguard of the Navy's Hedge Strategy, within the General-Purpose Force handling routine missions across the globe and freeing the Main Battle Force to remain focused on high-end combat. FF(X) will act as the command ship for Tailored Offsets, specifically Robotic and Autonomous Systems (RAS), and integrating with RAS to lead Tailored Forces into a cohesive warfighting approach. As the low-end anchor of the Golden Fleet high-low mix, the Frigate will relieve high end assets such as Arleigh Burke-Class destroyers from missions that do not require large multi mission combatants, including maritime interdiction and counter drug operations. Its primary role is to execute surface warfare, Counter-Unmanned Aerial Systems (C-UAS), and Command and Control (C2) of Unmanned Systems missions as well as others as enabled through containerized payloads, all through a highly producible, cost effective and adaptable platform. These containerized payload capabilities are aligned with and supported by the Navy's dedicated containerized payloads program, enabling rapid integration and fielding of mission modules, including containerized Vertical Launch System (VLS) payloads. This ensures that while Flight I of the FF(X) Class (currently planned as at least the first 2 ships) does not incorporate a traditional fixed VLS battery, it retains the capability to deploy VLS-equivalent payloads through modular, mission-tailored configurations. To deliver at speed and scale, the Navy is acquiring its new class of Frigates based on Huntington Ingalls Industry's (HII) Legend-class National Security Cutter (NSC) design - a proven American built ship that has been operational for 17 years with ten delivered cutters, protecting U.S. interests at home and abroad.
- Product Development
- Support
- Test and Evaluation
- Management Services
Frigate — one RDT&E project inside PE 0603599N. Congressional marks are recorded on the program element, not on a project.
Project 3086 — Frigate — requests $0.0M in FY2027, 0.0% of the $212.0M requested for program element 0603599N.
Project 3086 funding, FY2025–FY2031
Prior years are actuals, the budget year is the request, and the outyears are the FYDP plan. Estimate types are colored and never summed into one figure. Projects carry the full five-year plan; the activities inside them stop at the budget year.
| Fiscal Year | Estimate Type | Amount ($M) |
|---|---|---|
| FY2025 | Actual | 103.2 |
| FY2026 | Enacted | 0.0 |
| FY2027 | Request | 0.0 |
| FY2028 | Outyear | 0.0 |
| FY2029 | Outyear | 0.0 |
| FY2030 | Outyear | 0.0 |
| FY2031 | Outyear | 0.0 |
2 accomplishments / planned programs
The R-2A exhibit. Activities carry the prior, current and budget year only — no five-year plan — and they are descriptive: coverage is partial and they do not always add back to the project, so count them, never total them.
What project 3086 buys
The Navy reached a comprehensive settlement to terminate the last four ships of the Constellation Class Frigate Program (FFG 63-67) with the prime contractor. While work continues on the first two ships, USS Constellation (FFG 62) and USS Congress (FFG 63), those ships remain under Navy review. No funds are requested for the continuation of the Constellation FFGs under Project Unit (PU) 3086.
- Product Development
- Support
- Test and Evaluation
- Management Services