RDT&E Program Element · President's Budget PB2027

Small/Medium Unmanned Undersea Vehicles

PE 0604028N·U.S. Navy·Approp. 1319 — RDT&E·BA4 — Advanced Component Development & Prototypes
FY2027 Request
$24.6M
◆ Restart — nothing enacted in FY2026
HitchAI read

U.S. Navy requests $24.6M in FY2027 against nothing enacted in FY2026. In the FY2027 defense authorization, the House funded it in full; the Senate added 407% (to $124.6M); House appropriators added 78% (to $43.9M). Huntington Ingalls leads the industry work.

FY2027 Request
$24.6M
No FY2026 funding
FY2026 Enacted
$0.0M
▼ 100% vs FY2025
FY2025 Actual
$51.8M
Prior year

Roll-up of 6 projects. Projects are the summable leaves — the PE total is their sum, never added to it.

For fiscal year 2027, the U.S. Navy is requesting $24.6M for Small/Medium Unmanned Undersea Vehicles under RDT&E program element 0604028N, against nothing enacted in FY2026.

Funding trajectory

Funding profile, FY2025–FY2031

Prior years are actuals, the budget year is the request, and the outyears are the FYDP plan. Estimate types are colored and never summed into one figure.

2550051.8FY25ACTUAL0.0FY26ENACTED24.6FY27REQUEST17.6FY2816.3FY2915.4FY3015.7FY31
Actual Enacted Request Outyear (FYDP)
Fiscal YearEstimate TypeAmount ($M)
FY2025Actual51.8
FY2026Enacted0.0
FY2027Request24.6
FY2028Outyear17.6
FY2029Outyear16.3
FY2030Outyear15.4
FY2031Outyear15.7
Where it sits

Acquisition lifecycle

This program is funded in RDT&E Budget Activity 4 — Advanced Component Development & Prototypes.

Complete
Research
BA 1–2
Complete
Advanced Technology
BA 3
Current
Prototyping
BA 4
Later
Development & Fielding
BA 5–7
Inside the program element

6 projects roll up into PE 0604028N

Projects are the summable leaves — the PE total is their sum, never added to it. Program elements and projects carry the full five-year plan; activities stop at the budget year.

Congressional action

Congressional marks

Committee marks on the FY2027 request. Adds and cuts are reconciled in conference before they become law.

RequestPresident's Budget
$24.6M
House NDAA (HASC)HASC
$24.6M full · +$0
Senate NDAA (SASC)SASC
$124.6M +$100.0M · +407%
House Approps (HAC-D)HAC_D
$43.9M +$19.3M · +78%
▲ $100.0M chamber gap — unresolved as of 2026-07-27. These are FY2027 authorization marks (NDAA); appropriations and the conference agreement may differ.
Who's building it

Where the FY2027 request goes

Performers named in the R-3 exhibit, resolved into industry, government-lab, and unspecified shares. Budget-justification contract funding, not obligations.

Huntington Ingalls
$5.9M · 24%
RAZORBACK Product Development - MK19 · CPAF
NIWC PAC
$4.8M · 20%
Product Development · BA
Where FY2027 funding flowsShare$M
Industry primes73%17.8
Government labs & warfare centers22%5.5
Other / unspecified5.1%1.3
FY2027 request100%24.6
See Huntington Ingalls's full federal contract ledger members
Program detail

Mission & acquisition strategy

The Department encourages additional vendor participation in the design, development, and production of alternative weapons systems to meet current and future warfighting requirements. With current major weapons systems production at capacity, the nation is looking for alternative systems to fill these gaps. The Department is implementing diverse procurement strategies to enable rapid acquisition. These will include the use of Other Transaction Authorities, 'Marketplace' acquisition platforms, and alternative concepts to increase supply and suppliers in addition to traditional FAR-based procurement strategies.

The Knifefish program, initiated in FY11 and competitively sourced to General Dynamics Mission Systems (GDMS), develops Surface Mine Countermeasures Unmanned Undersea Vehicles (SMCM UUVs) equipped with advanced Low Frequency Broadband (LFBB) sonar to provide volume, bottom, and buried mine detection capability, in high clutter environments, when operated from the Littoral Combat Ship (LCS) Mine Countermeasures Mission Package (MCM MP) or Vessel of Opportunity (VOO). An Engineering Development Model (EDM) system was fabricated and tested through Developmental Testing (DT).

Project 1036, 3785, 2482, 2483, 3123, 4023 — TETRA
  • Product Development
  • Test and Evaluation
Ask Hitch

Ask this program element

Answers are generated from the figures on this page — the FY2027 justification exhibits and the marks tracked above — and nothing else is consulted. Confirm any figure against the cited exhibit before you use it externally.

H
Questions this page can answer
How does the FY2027 request compare with FY2026, and what does the five-year plan show?What did the FY2027 NDAA committees do to this request?Which project inside PE 0604028N is growing fastest, and which is shrinking?How is the FY2027 request split between industry and government performers?

This page carries the budget justification and the NDAA marks — nothing else. For what Huntington Ingalls has actually been obligated, the ledger is at hitchintel.com/vendors; for live solicitations, hitchintel.com/opportunities. Both are member surfaces.

Provenance

Cite this page

Sources
FY2027 Department of the Navy RDT&E Budget Justification · Exhibits R-2 / R-3 · PE 0604028N (President's Budget PB2027) — and FY2027 NDAA committee marks, as tracked 2026-07-27.
Suggested citation
HitchAI, "Small/Medium Unmanned Undersea Vehicles (PE 0604028N)," federal budget intelligence, PB2027 vintage. hitchintel.com/programs/0604028N
Machine access
Markdown twin /programs/0604028N.md · MCP mcp.hitchintel.combudget_get_program_element, budget_get_cong_marks
FY2027 Request
$13.9M
No FY2026 funding
FY2026 Enacted
$0.0M
▼ 100% vs FY2025
FY2025 Actual
$5.3M
Prior year

TETRA — one RDT&E project inside PE 0604028N. Congressional marks are recorded on the program element, not on a project.

Project 1036 — TETRA — requests $13.9M in FY2027, 56% of the $24.6M requested for program element 0604028N.

Funding trajectory

Project 1036 funding, FY2025–FY2031

Prior years are actuals, the budget year is the request, and the outyears are the FYDP plan. Estimate types are colored and never summed into one figure. Projects carry the full five-year plan; the activities inside them stop at the budget year.

05.3FY25ACTUAL0.0FY26ENACTED13.9FY27REQUEST8.8FY289.5FY299.8FY3010.0FY31
Actual Enacted Request Outyear (FYDP)
Fiscal YearEstimate TypeAmount ($M)
FY2025Actual5.3
FY2026Enacted0.0
FY2027Request13.9
FY2028Outyear8.8
FY2029Outyear9.5
FY2030Outyear9.8
FY2031Outyear10.0
Inside the project

2 accomplishments / planned programs

The R-2A exhibit. Activities carry the prior, current and budget year only — no five-year plan — and they are descriptive: coverage is partial and they do not always add back to the project, so count them, never total them. Opening lines only here — the full year-by-year narrative is on the project page.

FY2025 actual$5.3M
FY2026 enacted$0.0M
FY2027 request$13.8M

(U) Continued support for installation planning and execution for a TETRA mission. Supporting offload from first TETRA mission. Continuing to investigate west-coast laydown areas to support urgent fleet capability needs as more TETRA Shipsets become available. (U) TETRA will continue to develop, build, integrate, test, and create…

Read the FY2027 plan →
Test & EvaluationRESTART
FY2025 actual$0.0M
FY2026 enacted$0.0M
FY2027 request$0.1M

(U) Continued testing support for TETRA efforts on tactically representative support crafts and test fixtures

Project 1036 — every activity in full →
Who's building it

Named performers on project 1036

Performers named in the R-3 exhibit under this project. Share is of the project's whole FY2027 R-3 total — the same denominator the program-element split uses, so the two read on one scale and will not sum to 100% when unnamed or government work is in the mix. Budget-justification contract funding, not obligations.

NIWC PAC
$4.8M · 35%
OII
$4.0M · 29%
Leidos
$3.2M · 23%
Project detail

What project 1036 buys

The FY 2026 budget for PU1036 / TETRA program included $0 of discretionary funding and $32,000k of mandatory funding for a total of $32,000K. The mandatory funds supported the development of Lanternfish - a deep Remotely Operated Vehicle (ROV) supporting Subsea Seabed Warfare (SSW) mission areas. Funding also supports the continuation of the TETRA ROV. TETRA funding supports additional payload design and integration, as well as supporting documentation for platform integration. Bootstrap funding was allocated for system improvement and continued testing. (U) The TETRA program is a continuation of efforts, realigned from Program Element (PE) 0604029N (UUV Core Technologies) Project Unit (PU) 4053 (UxS Platform) to PE 0604028N (Small/Medium Unmanned Undersea Vehicles) PU 1036 (TETRA) in FY25, and also includes payload development addressing emergent operational requirements. The large increase in FY27 is due to increased Fleet requirements for the systems. (U) This is the sole project unit that enables deployment of TETRA, which is an operationally relevant Remotely Operated Vehicle (ROV) that is launched, and recovered, from submarine torpedo tubes. TETRA is a ROV with the capacity for multiple mission payloads as a key enabler to Subsea Seabed Warfare (SSW) to locate, identify, and provide real-time payload employment to effect objects of interest as identified in the SSW Initial Capabilities Document (ICD). As a tethered system, TETRA will provide real-time operational data back to the platform and enable man-in-the-loop intervention to maximize the efficiency of a sortie. Experimentations will be conducted with Unmanned Undersea Vehicle Squadron One (UUVRON ONE), Special Reconnaissance Team - 2 (SRT 2), and Naval Special Warfare Group 8 (NSWG 8) utilizing government test events, lake testing, and barge tests to provide Fleet and acquisition stakeholders with relevant payload and vehicle employment to inform Concept of Operations (CONOP) and fielding decisions using platforms of opportunity. (U) This project line is utilized for the development, and integration, of payloads into the TETRA ROV. Funding is also required to begin integration into Submarine Warfare Federated Tactical System (SWFTS) to reduce TETRA's stowage footprint.

R-3 lines of work
  • Product Development
  • Test and Evaluation
FY2027 Request
$10.7M
No FY2026 funding
FY2026 Enacted
$0.0M
▼ 100% vs FY2025
FY2025 Actual
$17.2M
Prior year

Razorback — one RDT&E project inside PE 0604028N. Congressional marks are recorded on the program element, not on a project.

Project 3785 — Razorback — requests $10.7M in FY2027, 44% of the $24.6M requested for program element 0604028N.

Funding trajectory

Project 3785 funding, FY2025–FY2031

Prior years are actuals, the budget year is the request, and the outyears are the FYDP plan. Estimate types are colored and never summed into one figure. Projects carry the full five-year plan; the activities inside them stop at the budget year.

017.2FY25ACTUAL0.0FY26ENACTED10.7FY27REQUEST8.8FY286.9FY295.6FY305.7FY31
Actual Enacted Request Outyear (FYDP)
Fiscal YearEstimate TypeAmount ($M)
FY2025Actual17.2
FY2026Enacted0.0
FY2027Request10.7
FY2028Outyear8.8
FY2029Outyear6.9
FY2030Outyear5.6
FY2031Outyear5.7
Inside the project

3 accomplishments / planned programs

The R-2A exhibit. Activities carry the prior, current and budget year only — no five-year plan — and they are descriptive: coverage is partial and they do not always add back to the project, so count them, never total them. Opening lines only here — the full year-by-year narrative is on the project page.

Product Development - RazorbackRESTART
FY2025 actual$14.4M
FY2026 enacted$0.0M
FY2027 request$9.2M

Procurement of two next generation MK19 prototypes to perform environmental qualification testing and testing associated with TEMPALT upgrades. Perform test and evaluation of the MK19 mod 1 technical upgrades and next generation variants and initial operational assessments. Upon delivery of the two tech refresh EDMs, begin testing and…

SupportRESTART
FY2025 actual$2.3M
FY2026 enacted$0.0M
FY2027 request$0.3M

Continue to provide MK19 acquisition and engineering support for contract management activities and submarine integration efforts.

Management ServicesRESTART
FY2025 actual$0.5M
FY2026 enacted$0.0M
FY2027 request$1.3M

Continue to provide technical guidance, project planning, program management, financial and contracting management, and travel for contract administration and submarine integration efforts for the MK19 program.

Project 3785 — every activity in full →
Who's building it

Named performers on project 3785

Performers named in the R-3 exhibit under this project. Share is of the project's whole FY2027 R-3 total — the same denominator the program-element split uses, so the two read on one scale and will not sum to 100% when unnamed or government work is in the mix. Budget-justification contract funding, not obligations.

Huntington Ingalls
$5.9M · 55%
Project detail

What project 3785 buys

A part of the Family of UUVs, Razorback is a medium class UUV capable of persistent, autonomous, ocean sensing and data collection in support of Navy Subsea and Seabed Warfare (SSW) including Intelligence Preparation of the Operational Environment (IPOE) missions. The Razorback MK19 procurement began in FY 2017 and Fleet operational deployments began in FY 2021. Conversion to a torpedo tube launch and recovery (TTL&R) variant began in FY23. The development of formalized training products begin in FY 2026. Development efforts for the Next Generation variant of MK19 will begin in FY26 through a partnership with the Defense Innovation Unit (DIU). In order to deploy Razorback or other small or medium class UUVs from a host submarine platform with sufficient endurance to perform a desired mission, high energy density sources such as lithium-ion batteries are used. Consequently, safety is paramount and mitigation systems must be in place to prevent or stop a high energy casualty event. Shock and Fire Enclosure Capsule (SAFECAP) is being developed as an active mitigation strategy that includes a shock qualified capsule that aides in the launch and recovery of small and medium sized UUVs through the torpedo tube, including Razorback. SAFECAP effort was transferred from PE0604028N PU3785 to PE0604029 PU4053 in FY 2025. The FY 2026 budget for Razorback program included $0 of discretionary funding and $25,000,000 FY25 mandatory funding for a total of $25,000,000. The mandatory funds supported acquisition of two prototype next generation MK19 vehicles, technical analysis for integrating several capabilities into the prototype design, platform integration, PPR battery integration into MK19 Mod 1 baseline, IPOE payload development, west coast training readiness, and test and evaluation for MK19 mod 1 and next generation variants. The FY 2027 request for Razorback program includes $10,257,000 of discretionary funding and $0 mandatory funding for a total of $10,719,000. Further information for this reconciliation request will be provided in the Reconciliation Exhibit.

R-3 lines of work
  • Product Development
  • Support
  • Management Services
FY2027 Request
$0.0M
No FY2026 funding
FY2026 Enacted
$0.0M
▼ 100% vs FY2025
FY2025 Actual
$6.1M
Prior year

Small Unmanned Undersea Vehicles — one RDT&E project inside PE 0604028N. Congressional marks are recorded on the program element, not on a project.

Project 2482 — Small Unmanned Undersea Vehicles — requests $0.0M in FY2027, 0.0% of the $24.6M requested for program element 0604028N.

Funding trajectory

Project 2482 funding, FY2025–FY2031

Prior years are actuals, the budget year is the request, and the outyears are the FYDP plan. Estimate types are colored and never summed into one figure. Projects carry the full five-year plan; the activities inside them stop at the budget year.

06.1FY25ACTUAL0.0FY26ENACTED0.0FY27REQUEST0.0FY280.0FY290.0FY300.0FY31
Actual Enacted Request Outyear (FYDP)
Fiscal YearEstimate TypeAmount ($M)
FY2025Actual6.1
FY2026Enacted0.0
FY2027Request0.0
FY2028Outyear0.0
FY2029Outyear0.0
FY2030Outyear0.0
FY2031Outyear0.0
Inside the project

1 accomplishment / planned program

The R-2A exhibit. Activities carry the prior, current and budget year only — no five-year plan — and they are descriptive: coverage is partial and they do not always add back to the project, so count them, never total them.

SMALL UNMANNED UNDERWATER VEHICLES
FY2025 actual$6.1M
FY2026 enacted$0.0M
FY2027 request$0.0M
Project detail

What project 2482 buys

As part of the Expeditionary UUV Family of Systems (FoS) the LIONFISH UUV Program of Record develops advanced SUUVs to support myriad missions across warfare domains. The missions include; expeditionary mine countermeasures, expeditionary data collection and surveillance, and intelligence preparation of the environment (IPOE). Equipment includes vehicles and associated systems support equipment. Planned block upgrades include increased detection range capability, communications upgrades, automated target recognition, cybersecurity, autonomy and command and control improvements, additional launch and recovery abilities, increased operational depth, and payloads as required. FY2027 supports planned improvements for the vehicles now in full rate production, to include RDTE for advanced sensor packages, software development/ integration, automatic target recognition, and usability upgrades.

R-3 lines of work
  • Product Development
  • Support
  • Test and Evaluation
  • Management Services
FY2027 Request
$0.0M
No FY2026 funding
FY2026 Enacted
$0.0M
▼ 100% vs FY2025
FY2025 Actual
$9.0M
Prior year

Medusa — one RDT&E project inside PE 0604028N. Congressional marks are recorded on the program element, not on a project.

Project 2483 — Medusa — requests $0.0M in FY2027, 0.0% of the $24.6M requested for program element 0604028N.

Funding trajectory

Project 2483 funding, FY2025–FY2031

Prior years are actuals, the budget year is the request, and the outyears are the FYDP plan. Estimate types are colored and never summed into one figure. Projects carry the full five-year plan; the activities inside them stop at the budget year.

09.0FY25ACTUAL0.0FY26ENACTED0.0FY27REQUEST0.0FY280.0FY290.0FY300.0FY31
Actual Enacted Request Outyear (FYDP)
Fiscal YearEstimate TypeAmount ($M)
FY2025Actual9.0
FY2026Enacted0.0
FY2027Request0.0
FY2028Outyear0.0
FY2029Outyear0.0
FY2030Outyear0.0
FY2031Outyear0.0
Inside the project

3 accomplishments / planned programs

The R-2A exhibit. Activities carry the prior, current and budget year only — no five-year plan — and they are descriptive: coverage is partial and they do not always add back to the project, so count them, never total them.

MEDUSA Product Development
FY2025 actual$6.1M
FY2026 enacted$0.0M
FY2027 request$0.0M

FY2026 plans — current year Completion of MEDUSA prototype design through Critical Design Review (CDR). Continue essential engineering efforts to include; submarine integration, design reviews, payload integration.

MEDUSA Support
FY2025 actual$2.0M
FY2026 enacted$0.0M
FY2027 request$0.0M

FY2026 plans — current year Provide acquisition and engineering support for completion of MEDUSA design. Continue essential support efforts to include; system safety engineering activities, and Weapon Systems Explosive Safety Review Board (WSESRB) reviews.

MEDUSA Management Services
FY2025 actual$1.0M
FY2026 enacted$0.0M
FY2027 request$0.0M

FY2026 plans — current year Provide acquisition and engineering support for contract management activities, project planning, program management, financial management, and travel for contract administration and submarine integration efforts

Project detail

What project 2483 buys

MEDUSA is a medium class UUV capable of offensive mining capabilities deployed from a submarine. MEDUSA features torpedo tube launch capability, long range, high payload placement accuracy, and can support heavy payloads. A demonstration system was developed and tested in FY21 with dummy payloads using a land-based launch facility and surface launched in-water demonstrations. Lessons learned from the demonstration informed a program start in FY 2022 and competitive award to Industry in FY 2024. System design is in process with completion in FY2026. The FY 2026 budget for the MEDUSA program included $0 discretionary funding and $82,440,000 of FY25 mandatory funding for a total of $82,440,000. The mandatory funds supported the completion of prototype design, prototype procurement, Submarine integration and acquisition support. Further information for this reconciliation request will be provided in the Reconciliation Exhibit. FY2027 zero's funding for continued MEDUSA development and procurements. FY25 mandatory funding will be utilized to complete design and transition MEDUSA technologies.

R-3 lines of work
  • Product Development
  • Support
  • Management Services
FY2027 Request
$0.0M
No FY2026 funding
FY2026 Enacted
$0.0M
▼ 100% vs FY2025
FY2025 Actual
$1.9M
Prior year

SMCM UUV — one RDT&E project inside PE 0604028N. Congressional marks are recorded on the program element, not on a project.

Project 3123 — SMCM UUV — requests $0.0M in FY2027, 0.0% of the $24.6M requested for program element 0604028N.

Funding trajectory

Project 3123 funding, FY2025–FY2031

Prior years are actuals, the budget year is the request, and the outyears are the FYDP plan. Estimate types are colored and never summed into one figure. Projects carry the full five-year plan; the activities inside them stop at the budget year.

01.9FY25ACTUAL0.0FY26ENACTED0.0FY27REQUEST0.0FY280.0FY290.0FY300.0FY31
Actual Enacted Request Outyear (FYDP)
Fiscal YearEstimate TypeAmount ($M)
FY2025Actual1.9
FY2026Enacted0.0
FY2027Request0.0
FY2028Outyear0.0
FY2029Outyear0.0
FY2030Outyear0.0
FY2031Outyear0.0
Inside the project

1 accomplishment / planned program

The R-2A exhibit. Activities carry the prior, current and budget year only — no five-year plan — and they are descriptive: coverage is partial and they do not always add back to the project, so count them, never total them.

Knifefish Development
FY2025 actual$1.9M
FY2026 enacted$0.0M
FY2027 request$0.0M

FY2026 plans — current year BMH ERT realigned under Core Tech Payloads RDTEN PRJ 3395

Project detail

What project 3123 buys

As part of the UUV Family of Systems (FoS) and in support of the Mine Countermeasures (MCM) Mission Package (MP), the Surface Mine Countermeasures Unmanned Undersea Vehicle (SMCM UUV) Program, also referred to as Knifefish, develops advanced medium class UUVs to support clandestine mine detection capability against volume, bottom, and buried mines, in high clutter environments. Equipment includes UUVs and associated system support equipment. The program achieved Milestone C in FY 2019 and entered into Low-Rate Initial Production (LRIP) for five (5) Block 0 systems in FY 2019. The prime contractor for Knifefish is General Dynamics Mission Systems (GDMS) located in Quincy, MA. In FY 2021, GDMS was awarded a contract to retrofit the LRIP systems with Block 1 capabilities and upgrade a number of performance characteristics to meet Navy bottom and buried mine hunting requirements. The Navy will conduct a limited validation of these capabilities during system acceptance testing and sell off to the government in Q1-Q3FY24. Upon delivery of these systems to the Navy, they will be available for limited Fleet operations from LCS or Vessels of Opportunity (VOO).

R-3 lines of work
  • Product Development
  • Support
  • Test and Evaluation
  • Management Services
FY2027 Request
$0.0M
No FY2026 funding
FY2026 Enacted
$0.0M
▼ 100% vs FY2025
FY2025 Actual
$12.3M
Prior year

Expeditionary Underwater Systems — one RDT&E project inside PE 0604028N. Congressional marks are recorded on the program element, not on a project.

Project 4023 — Expeditionary Underwater Systems — requests $0.0M in FY2027, 0.0% of the $24.6M requested for program element 0604028N.

Funding trajectory

Project 4023 funding, FY2025–FY2031

Prior years are actuals, the budget year is the request, and the outyears are the FYDP plan. Estimate types are colored and never summed into one figure. Projects carry the full five-year plan; the activities inside them stop at the budget year.

012.3FY25ACTUAL0.0FY26ENACTED0.0FY27REQUEST0.0FY280.0FY290.0FY300.0FY31
Actual Enacted Request Outyear (FYDP)
Fiscal YearEstimate TypeAmount ($M)
FY2025Actual12.3
FY2026Enacted0.0
FY2027Request0.0
FY2028Outyear0.0
FY2029Outyear0.0
FY2030Outyear0.0
FY2031Outyear0.0
Inside the project

1 accomplishment / planned program

The R-2A exhibit. Activities carry the prior, current and budget year only — no five-year plan — and they are descriptive: coverage is partial and they do not always add back to the project, so count them, never total them.

Expeditionary UUV Family of Systems
FY2025 actual$12.3M
FY2026 enacted$0.0M
FY2027 request$0.0M
Project detail

What project 4023 buys

Funding supported the development of unmanned systems for the Navy's expeditionary unmanned underwater Explosive Ordnance Disposal (EOD) and Mine Countermeasures (MCM) capability. Specifically, it provided for development of expeditionary, unmanned underwater systems to support Navy Expeditionary forces including EOD, Mobile Diving and Salvage, Underwater Construction Teams (UCT), Very Shallow Water (VSW), and Expeditionary Mine Countermeasures (ExMCM) mission operations. The equipment was required to be highly portable in order to support the Navy EOD technician to safely approach, render safe, recover, exploit, and dispose of underwater explosive threats to include sea mines, limpet mines, and unexploded ordnance. Provided support for the Navy's high priority missions of Maritime Homeland Defense and MCM, including reconnaissance and mine clearance in support of amphibious operations. Development of Expeditionary UUV systems supported localization render-safe and detailed intelligence gathering of unexploded ordnance (UXO) including Underwater Improvised Explosive Devices (IEDs). This project directly supported the requirements defined by the Maritime Expeditionary MCM UUV (MEMUUV) CDD. Viperfish UUV is an incremental increase in capability from MK 18 MOD 2. It will leverage volume and bottom mine hunting capabilities, increase endurance from the Mod 2 system, increased depth capability, and will have embedded automated target recognition (ATR).

R-3 lines of work
  • Product Development
  • Support
  • Test and Evaluation
  • Management Services