RDT&E Program Element · President's Budget PB2027

Facility Restoration and Modernization - T&E

PE 0605976F·U.S. Air Force·Approp. 3600 — RDT&E·BA6 — RDT&E Management Support
FY2027 Request
$367.4M
◆ Scaling +84%
HitchAI read

U.S. Air Force funding ramps 84% to a $367.4M request in FY2027 — the program's peak. In the FY2027 defense authorization, the House funded it in full; the Senate funded it in full; House appropriators funded it in full.

FY2027 Request
$367.4M
▲ 84% vs FY2026
FY2026 Enacted
$199.4M
▲ 110% vs FY2025
FY2025 Actual
$94.8M
Prior year

For fiscal year 2027, the U.S. Air Force is requesting $367.4M for Facility Restoration and Modernization - T&E under RDT&E program element 0605976F, up 84% over FY2026.

Funding trajectory

Funding profile, FY2025–FY2031

Prior years are actuals, the budget year is the request, and the outyears are the FYDP plan. Estimate types are colored and never summed into one figure.

100200300094.8FY25ACTUAL199.4FY26ENACTED367.4FY27REQUEST314.3FY28284.0FY29288.9FY30273.4FY31
Actual Enacted Request Outyear (FYDP)
Fiscal YearEstimate TypeAmount ($M)
FY2025Actual94.8
FY2026Enacted199.4
FY2027Request367.4
FY2028Outyear314.3
FY2029Outyear284.0
FY2030Outyear288.9
FY2031Outyear273.4
Where it sits

Acquisition lifecycle

This program is funded in RDT&E Budget Activity 6 — RDT&E Management Support.

Complete
Research
BA 1–2
Complete
Advanced Technology
BA 3
Complete
Prototyping
BA 4
Current
Development & Fielding
BA 5–7
Inside the program element

1 project rolls up into PE 0605976F

Projects are the summable leaves — the PE total is their sum, never added to it. Program elements and projects carry the full five-year plan; activities stop at the budget year. This PE moves 84% overall, which can hide much larger swings below.

Project 6606MC

Facility Restoration and Modernization - T&E

$367.4MFY2027 request ▲ 84%
FY2025 actual$94.8M
FY2026 enacted$199.4M
FY2027 request$367.4M

This program element included all necessary expenses required to manage, execute, and deliver weapon system capability. The use of such program funds would be in addition to the civilian pay expenses budgeted in program element 0605807F. Restoration includes repair or replacement work to restore facilities damaged by inadequate sustainment, excessive age, natural disaster, fire, accident, or other causes. Modernization includes alteration or replacement of facilities to implement new or higher standards, to accommodate new functions, or to replace aging building components that typically last more than 50 years (such as framework or foundation). Environmental compliance costs, facility leases, and other tasks associated with facilities operations (such as custodial services, grounds services, waste disposal and the provision of central utilities) are not included. Restoration/modernization funds support the following Air Force test organizations and their associated test and evaluation facilities: the 96th Test Wing (TW) at Eglin AFB, FL; the 412TW at Edwards AFB, CA; and the Arnold Engineering and Development Complex (AEDC), to include assets at Arnold AFB, TN, the 704th Test Group (TG) at Holloman AFB, NM, the 704TG Landing Gear Test Facility (LGTF) at Wright-Patterson AFB, OH, the Hypersonic Wind Tunnel 9 at White Oak, MD, and the National Full-Scale Aerodynamics Complex (NFAC) at Moffett Field, CA. This program is in Budget Activity 6, RDT&E Management Support because this budget activity includes research, development, test and evaluation efforts and funds to sustain and/or modernize the installations or operations required for general research, development, test and evaluation.

Accomplishments / planned programs (R-2A) — prior, current and budget year only
FY2025 actual$14.3M
FY2026 enacted$15.8M
FY2027 request$10.5M

96 TW FY 2027 Budget Year plans include HVAC, plumbing, and electrical facility system repairs for multiple test facilities; planning charettes for the range communications facility; fluid replacement and storm damage repair at McKinley Climatic Laboratory; multiple roof replacements; and planning charrette/design/construction for…

Read the FY2027 plan →
FY2025 actual$70.6M
FY2026 enacted$176.7M
FY2027 request$345.5M

AEDC FY 2027 Budget Year plans include major restoration and modernization stopgap measures at the Central Inertial and GPS Test Facility (CIGTF) the Holloman High Speed Test Track (HHSTT), and the National Radar Cross-Section Test Facility (NRTF) as bridges to future MILCONs; major shared mechanical, electrical, and cooling water system…

Read the FY2027 plan →
FY2025 actual$10.0M
FY2026 enacted$6.9M
FY2027 request$11.4M

412 TW FY 2027 Budget Year plans include multiple phased secure facility, power, and test cooling system upgrades for the Benefield Anechoic Facility; multiple upgrades to the test engineering software lab to include HVAC replacement, safety/security improvements, fire suppression system replacement and renovation of the warehouse…

Read the FY2027 plan →
Congressional action

Congressional marks

Committee marks on the FY2027 request. Adds and cuts are reconciled in conference before they become law.

RequestPresident's Budget
$367.4M
House NDAA (HASC)HASC
$367.4M full · +$0
Senate NDAA (SASC)SASC
$367.4M full · +$0
House Approps (HAC-D)HAC_D
$367.4M full · +$0
unresolved as of 2026-07-27. These are FY2027 authorization marks (NDAA); appropriations and the conference agreement may differ.
Ask Hitch

Ask this program element

Answers are generated from the figures on this page — the FY2027 justification exhibits and the marks tracked above — and nothing else is consulted. Confirm any figure against the cited exhibit before you use it externally.

H
Questions this page can answer
How does the FY2027 request compare with FY2026, and what does the five-year plan show?What did the FY2027 NDAA committees do to this request?

This page carries the budget justification and the NDAA marks — nothing else. For what a contractor has actually been obligated, the ledger is at hitchintel.com/vendors; for live solicitations, hitchintel.com/opportunities. Both are member surfaces.

Provenance

Cite this page

Sources
FY2027 Department of the Air Force RDT&E Budget Justification · Exhibits R-2 / R-3 · PE 0605976F (President's Budget PB2027) — and FY2027 NDAA committee marks, as tracked 2026-07-27.
Suggested citation
HitchAI, "Facility Restoration and Modernization - T&E (PE 0605976F)," federal budget intelligence, PB2027 vintage. hitchintel.com/programs/0605976F