RDT&E Program Element · President's Budget PB2027

Armored System Modernization - Adv Dev

PE 0603645A·U.S. Army·Approp. 2040 — RDT&E·BA4 — Advanced Component Development & Prototypes
FY2027 Request
$23.6M
Army · RDT&E
HitchAI read

U.S. Army requests $23.6M in FY2027, sustained across the five-year plan. In the FY2027 defense authorization, the House funded it in full; the Senate funded it in full; House appropriators funded it in full. PM/Program Executive Office/GVSC leads the industry work.

FY2027 Request
$23.6M
▲ 4.2% vs FY2026
FY2026 Enacted
$22.6M
▲ 1.2% vs FY2025
FY2025 Actual
$22.4M
Prior year

For fiscal year 2027, the U.S. Army is requesting $23.6M for Armored System Modernization - Adv Dev under RDT&E program element 0603645A, up 4.2% over FY2026.

Funding trajectory

Funding profile, FY2025–FY2031

Prior years are actuals, the budget year is the request, and the outyears are the FYDP plan. Estimate types are colored and never summed into one figure.

022.4FY25ACTUAL22.6FY26ENACTED23.6FY27REQUEST23.6FY2823.8FY2923.6FY3024.0FY31
Actual Enacted Request Outyear (FYDP)
Fiscal YearEstimate TypeAmount ($M)
FY2025Actual22.4
FY2026Enacted22.6
FY2027Request23.6
FY2028Outyear23.6
FY2029Outyear23.8
FY2030Outyear23.6
FY2031Outyear24.0
Where it sits

Acquisition lifecycle

This program is funded in RDT&E Budget Activity 4 — Advanced Component Development & Prototypes.

Complete
Research
BA 1–2
Complete
Advanced Technology
BA 3
Current
Prototyping
BA 4
Later
Development & Fielding
BA 5–7
Inside the program element

1 project rolls up into PE 0603645A

Projects are the summable leaves — the PE total is their sum, never added to it. Program elements and projects carry the full five-year plan; activities stop at the budget year. This PE moves 4% overall, which can hide much larger swings below.

Project EV7

Combat Vehicle Prototyping

$23.6MFY2027 request ▲ 4%
FY2025 actual$22.4M
FY2026 enacted$22.6M
FY2027 request$23.6M
Product DevelopmentSupportTest and Evaluation

Armored System Modernization Advanced Development will continue the maturation of emerging ground combat vehicle capabilities to provide a bridge from S&T investment to application on a vehicle platform, informing requirements through User Evaluations, identification of capability gaps and reduction of integration risks. Maturing emerging technologies like those in Project Convergence Capstone (PCC) will enable ground combat platforms to meet the Army's strategy of fielding key Modernization efforts. The funding will support virtual and physical concept development, trade studies, technical and operational analyses to assess future concepts and designs. This would also include the support for survivability, lethality and other soldier defined system requirements. In addition, this funding will provide program management, expertise and a business process for the maturation and transition of emerging Science and Technology systems, system integration labs, technology demonstration efforts risk reduction, maturation, testing and assessment, and develop and integrate systems for Capability Program Executive (CPE) Ground platforms.

Accomplishments / planned programs (R-2A) — prior, current and budget year only
Government Engineering & Program Managementflat
FY2025 actual$2.5M
FY2026 enacted$2.7M
FY2027 request$2.7M

FY2027 planned work This funding will support Government oversight and project management of planned efforts which will cover government salaries, contractor labor, travel, training, supplies, equipment and facilities costs.

FY2026 plans — current year This funding will support Government oversight and project management of planned efforts which will cover government salaries, contractor labor, travel, training, supplies, equipment and facilities costs.

FY2025 accomplishments This funding will support Government oversight and project management of planned efforts which will cover government salaries, contractor labor, travel, training, supplies, equipment and facilities costs.

FY2025 actual$7.6M
FY2026 enacted$10.3M
FY2027 request$19.9M

This funding will further refine Developmental Engineering efforts to include but not limited to Advanced Combat Vehicle Concepts, enable faster prototyping and fielding of critical capabilities, integrate emerging technology into formations to innovate, and refine requirements with Vehicle Excursions, Aided Target Detection and…

Read the FY2027 plan →
Test & Evaluation▼ 90%
FY2025 actual$12.3M
FY2026 enacted$9.6M
FY2027 request$1.0M

FY2027 planned work This funding includes test and evaluation efforts to Vehicle Excursions, soldier assessment efforts, Aided Target Detection and Recognition (AiTDR), Segmented Composite Rubber Track (S-CRT), Virtual Operator/Maintainer, Virtual Fielding, Active Protection System Sensing (APS), and other emerging combat vehicle technology advancements to assist in determining future requirements while evaluating maturation level and aid in determination of bridging S&T efforts to vehicle platforms.

FY2026 to FY2027 change FY 2027 funding decrease is due to completion of Advanced Combat Powertrain testing, Combat Vehicle Light-weighting, and other testing activities.

FY2026 plans — current year This funding includes test and evaluation efforts to MUM-T Protected Comms, Combat Vehicle Light-weighting, Compound Eye, Aided Target Detection and Recognition (AiTDR), Segmented Composite Rubber Track (S-CRT), XM913 testing, Virtual Operator/Maintainer, Active Protection System Sensing (APS) and other emerging combat vehicle technology advancements to assist in determining future requirements while evaluating maturation level and aid in determination of bridging S&T efforts to vehicle platforms.

FY2025 accomplishments T&E efforts included but were not limited to: Combat Optimization for Robotic Systems, Autonomy, Integration, and Reliability (CORSAIR) soldier assessment efforts, Advanced Combat Powertrain Maturation, Combat Vehicle Light-weighting, Tank Modernization, MUM-T Protected Comms, Virtual Fielding, Vehicle Excursions, Active Protection System Sensing (APS), Aided Target Recognition (AiTR), small-scale, system-of-system demonstrations and other emerging combat vehicle technology advancements to assist in determining future requirements while evaluating maturation level and aid in determination of bridging S&T efforts to vehicle platforms.

Congressional action

Congressional marks

Committee marks on the FY2027 request. Adds and cuts are reconciled in conference before they become law.

RequestPresident's Budget
$23.6M
House NDAA (HASC)HASC
$23.6M full · +$0
Senate NDAA (SASC)SASC
$23.6M full · +$0
House Approps (HAC-D)HAC_D
$23.6M full · +$0
unresolved as of 2026-07-27. These are FY2027 authorization marks (NDAA); appropriations and the conference agreement may differ.
Who's building it

Where the FY2027 request goes

Performers named in the R-3 exhibit, resolved into industry, government-lab, and unspecified shares. Budget-justification contract funding, not obligations.

PM/Program Executive Office/GVSC
$2.7M · 11%
Program Management
Where FY2027 funding flowsShare$M
Industry primes11%2.7
Other / unspecified89%20.9
FY2027 request100%23.6
See PM/Program Executive Office/GVSC's full federal contract ledger members
Program detail

Mission & acquisition strategy

Armored System Modernization Advanced Development will continue the maturation of emerging ground combat vehicle capabilities to provide a bridge from S&T investment to application on a vehicle platform, informing requirements through User Evaluations, identification of capability gaps and reduction of integration risks. Maturing emerging technologies like those in Project Convergence Capstone (PCC) will enable ground combat platforms to meet the Army's strategy of fielding key Modernization efforts. The funding will support virtual and physical concept development, trade studies, technical and operational analyses to assess future concepts and designs.

These level of efforts provide the focused investment for the development and demonstration of technology and prototyping for future combat vehicles in the battlefield. The intent of this funding is to mature the next generation of technology which will enable demonstration of capabilities developed in the S&T portfolio to meet emerging military needs across the current Army portfolio of ground vehicles.

Project EV7 — Combat Vehicle Prototyping
  • Product Development
  • Support
  • Test and Evaluation
Ask Hitch

Ask this program element

Answers are generated from the figures on this page — the FY2027 justification exhibits and the marks tracked above — and nothing else is consulted. Confirm any figure against the cited exhibit before you use it externally.

H
Questions this page can answer
How does the FY2027 request compare with FY2026, and what does the five-year plan show?What did the FY2027 NDAA committees do to this request?How is the FY2027 request split between industry and government performers?In plain terms, what is this program element for and how is it being acquired?

This page carries the budget justification and the NDAA marks — nothing else. For what PM/Program Executive Office/GVSC has actually been obligated, the ledger is at hitchintel.com/vendors; for live solicitations, hitchintel.com/opportunities. Both are member surfaces.

Provenance

Cite this page

Sources
FY2027 Department of the Army RDT&E Budget Justification · Exhibits R-2 / R-3 · PE 0603645A (President's Budget PB2027) — and FY2027 NDAA committee marks, as tracked 2026-07-27.
Suggested citation
HitchAI, "Armored System Modernization - Adv Dev (PE 0603645A)," federal budget intelligence, PB2027 vintage. hitchintel.com/programs/0603645A
Machine access
Markdown twin /programs/0603645A.md · MCP mcp.hitchintel.combudget_get_program_element, budget_get_cong_marks